BOLD 3.
Index Cabinets 72in Wall Mounted Rack Project Centre
IM-PB3.01A-06 Bold 3.0 Warning: Excessive weight hazard! WARNING: Excessive weight hazard! Use two or more people to move, assemble or install cabinets and locker to avoid back injury. Do not leave children nearpeople cabinets.to High risk ofassemble, tipping if cabinets are installed Useunattended two or more move, or install cabinets and incorrectly: securely attach cabinets to the wall to avoid serious injury. locker to avoid back injury.
Index Index Guidelines and Weight Capacity Parts List Tools Needed Warranty Attaching Feet Attaching Casters Removing and Inserting Drawers Installing Corner Cabinet Stacking Cabinets Installing Worktop Support Bracket Attaching Worktop to Cabinets Installing Shelves Securing Cabinets to Drywall/Stud Wall Hanging Cabinets on Slatwall Fastening Cabinets Together Attaching Light Valance Utility Hole Grommet 2 2 3 3 5 5 6 7 8 9 10 11 12 13 14 15 16 18 19
Worktop 21” Corner Worktop 48” Worktop. Fits over 2 Cabinets 72” Worktop. Fits over 3 Cabinets Weight Capacity 150 lbs. NOTE: Claimed weight capacities are only with NewAge worktops installed 250 lbs per foot. 1000 lbs. per Set of 4 Wall Cabinets Max 100 lbs. 200 lbs. 200 lbs. 200 lbs. 100 lbs. 100 lbs. 200 lbs. 4in Casters 250 lbs. / caster 600 lbs. / set of 4 100 lbs. Base Cabinets Max 600 lbs. 100 lbs. 150 lbs. 150 lbs. 150 lbs. 100 lbs. 200 lbs. Tool Cabinets Max 600 lbs.
Unpacking • Begin by placing the package on a covered flat surface. • Remove all cardboard, foam packaging material and clear plastic bags. • Dispose / recycle all packaging materials. • Verify all the contents in the box and gather the required tools. See “Parts” and “Tools Needed” in the list below. Parts Supplied Type Hardware 30-in. Locker 42-in. Locker #8 x 5/8" Wood Screw 1/4" ID x 1/2" OD Washer Spring Washer 1/4" Lock Nut 1/4" x 0.9" Fender Washer Hardware Pack 1/4" x 2.
Tools Needed 1 x Adjustable wrench 1 x 12” Magnetic Leveler 1 x Stud Finder 1 x Tape Measure 3 2 1 1 1 x 7/16” Socket driver wrench 1 x 8mm” Socket driver 1 x 7/16” socket wrench 2 3 1 x Set Square 1 x Pencil 1 x #2 Phillips Bit 1 x Cordless Power Drill 1 x Hammer Drill 1 x Masonry Bit 1 x #2 Phillips 1 x #3 Phillips head screw driver head screw driver [optional for masonry] Manufacturer Warranty Limited Lifetime When this product is installed, operated and maintained according to the instruct
Installing the Feet 1 Parts Needed. 16 X Foot Attachment Screws 4 X Foot 2 Flip cabinet upside down, locate holes at corners. 3 4 Repeat step 3 for each corner. 5 6 Open cabinet, remove any shelves or loose items. Align foot with edge of cabinet. Screw in 4 x foot attachment screws using #3 philips screwdriver. Stand & level feet.
Installing Casters Parts Needed. 4 x Casters 16 X Hex Bolt (1/4” x 5/8”) 32 X Washer (1/4”) 16 X Lock Nut (1/4”) Note: Casters sold seperately. 1 2 Flip cabinet upside down, locate holes forming a square. 3 4 Repeat steps 3 for each corner. 5 Open cabinet, remove any shelves or loose items.
Installing the Drawers Inserting Drawers. Align Rails Slide In Removing Drawers.
Installing Corner Cabinet 1 Parts Needed. Lock Nut (1/4”) Wall Washer (1/4”) # 8 x 5/8” Screw 1/4” x 5/8 Hex Bolt Note: Ensure there is enough assembly room. Cabinets must be assembled away from corner to access backs of cabinets. On adjacent edges attach 2 support brackets to underside of corner top using the supplied (4) #8 x 5/8” screws. A 3 2 B 1 1 2 Attach top to one cabinet using 1/4” x 5/8 hex bolts, nuts, and washers. 4 Slide in corner and attach remaining cabinets.
Stacking Cabinets Parts Needed. 1 Position a second base cabinet on top of an existing base cabinet. 4 X Hex Bolt (1/4” x 5/8”) I 8 X Washer (1/4”) 4 X Lock Nut (1/4”) 2 Locate punch holes on adjoining surface and insert bolts. 4 Tighten all bolts 10 3 Attach cabinets using the supplied 1/4” x 5/8” hex bolts, washers, and nuts.
Installing Worktop Side Support Bracket Parts Needed. 2 Support Bracket 2 X Hex Bolt (1/4” x 5/8”) 4 X Washer (1/4”) 2 X Lock Nut (1/4”) 1 Note: Support Bracket Sold Separately A support bracket is to be used if the worktop is added to the set without a secondary supporting base/tool cabinet. Open locker and locate holes on either side. Align bracket. 3 Fasten nuts, bolts, and lock washers. X2 5 Level bracket and ensure it is at the same height as the base cabinet. 4 Tighten nuts & bolts.
Mounting the Worktop (On 2 Cabinets) 1 Place worktop on cabinets. 2 Locate 2 punch holes both sides. X2 X2 I 3 Drill into the worktop using the #8 x 5/8” wood screws. Optional: For locker support bracket. X4 Use 2 washers & #8 x 5/8” wood screws. Provided in the locker packaging.
Inserting Cabinet Shelves 1 Stand cabinet up. 2 Insert shelf at a slight angle. 3 Level shelf. 4 Lower shelf onto brackets by sliding tabs into slots. 5 Ensure shelf is clipped in position. 6 Insert remaining shelves.
Mounting Cabinets (Drywall/Studded Wall) Parts Required Wall Screw (1/4” x 2.5”) 1 Use stud finder to locate the studs and mark the wall with a pencil. Wall Washer (1/4”) Wall & Locker: 4 wall screws and 4 washers Corner Wall: 6 wall screws and 6 washers Base & Tool Cabinet: 2 wall Screws and 2 washers 2 Place cabinet tight against the wall. 5 Drill 4 wall screws and washers through perforated holes into studs. 3 Align cabinet to stud marks. X4 14 4 Level cabinet by adjusting feet Masonry.
Hanging Cabinets on Slatwall Note: Slatwall Brackets for use with standard 3” slatwall Sold Separately. Check with your slatwall supplier to determine the rated capacity of your slatwall. DO NOT OVERLOAD. NewAge Slatwall Brackets are only compatible with standard 3” on center Slatwall. 1 Parts Needed. 3 X Hex Bolt (1/4” x 5/8”) Insert bolts through slatwall bracket. Slatwall Bracket 3x Wall Washer (1/4”) 3x Lock Nut (1/4”) 2 Attach braket to slatwall at desired height.
Fastening Cabinets Parts Needed. 1 Note: Fasten additional cabinets to initial securely mounted cabinet. Align bolts, tighten lightly. Hex Bolt (1/4” x 5/8”) Washer (1/4”) Lock Nut (1/4”) X4 X4 Note: Remove all drawers before fastening cabinets 2 16 Level cabinets and tighten all bolts.
Attaching Light Valance to Wall Cabinet 1 Align holes of valance with cabinet. 3 Cross Section View 2 Insert and tighten bolt and nuts. Parts Needed.
Utility Access 1 Insert rubber grommet into cut-out hole in bottom panel. 2 The utility access hole allows easy connection to power outlet. Thank you for purchasing a NewAge Product! Please give us a call or visit online if you have any questions. Call 1.877.306.8930; for UK 0800.031.4069; e-mail at info@newageproducts.
IM-PB3.01A-06 Série Bold 3.0 AVERTISSEMENT: Avertissement : Risque de poids excessif! RISQUE DE POIDS EXCESSIF! Déplacer, assembler ou installer les armoires et armoires-vestiaires avec l'aide de deux personnes ou plus. Dans le cas contraire, il pourrait en découler des blessures au dos ou autre. Ne pas laisser les enfants sans surveillance près des armoires.
Index Index Capacités poids Pièces fournies Outils nécessaires Garantie Installation des pieds Installation des roulettes Instalation des tiroirs Installation des armoires Emboîtement des armoires de coin Installation du palier de support latéral du plan de travail Montage du plan de travail( sur 2 armoires) Insertion des étagères d”armoire Assemblage des armoires( cloison seche et cloison creuse a colombage) Fixation des armoires sur une paroi a lattes Raccord des armoires Fixer le cache-néon a l’armoire m
Plan de travail Plan de travail d’angle de 21 po Plan de travail de 48 po. Convient à 2 armoires Plan de travail de 72 po. Convient à 3 armoires Capacité de poides 68kg (150 lb) 45kg (100 lb) REMARQUE: Les capacités de poids déclarées ne concernent que les plans de travail Newage installés. 90 kg (200 lb) 250 lbs par pied. 1000 lbs. par armoires Roulettes 4po 250 lbs. par roulettes 600 lbs. par armoires Armoires murales Max.
Déballage • Commencer par placer la boîte sur une surface plate recouverte. • Retirer tout le carton, le matériel d’emballage en mousse et les sacs en plastique transparent. • Mettre au rebus ou recycler tous les matériaux d’emballage. • Vérifier tout le contenu de la boîte et rassembler les outils nécessaires. Voir Pièces fournies et Outils nécessaires ci-dessous.
Outils nécessaires 1 x clé ajustable 1 x vérin magnétique de 12 po 1 x localisateur de montants 1 x ruban à mesurer 3 2 1 1 1 x cle a doiulles de 1 x cle a douilles de 1 x douille de 7/16 po 8mm 7/16 po 1 x tournevis 1 x tournevis cruciforme cruciforme Philips #2 Philips #3 2 3 1 x équerre 1 x crayon à dessin 1 x perceuse mecanique sans fil 1 x tournevis Phillips #2 1 x marteau 1 x meche à maçonnerie perforateur [facultatif pour la maçonnerie] Garantie à vie limitée du fabricant Lorsque ce pro
Installation des pieds 1 Ouvrir l’armoire et retirer les étagères ou les objets épars. 2 Retourner l’armoire et repérer les trous dans les coins. 3 Aligner le pied sur le bord de l’armoire. Visser 4 vis à sécurités dans les trous. 4 Répéter l’étape 3 pour chaque coin. 5 Pièces nécessaires. 16 X Foot Vis à sécurite 6 4 x pieds Remettre à l’endroit et niveler.
Installation des roulettes Remarque : Les rondelles sont vendues séparément. 1 Ouvrir l’armoire et retirer les étagères ou les objets épars. 2 Retourner l’armoire et repérer les trous formant un carré. 3 Aligner le pied sur les trous. Fixer avec les 4 boulons à tête hexagonale de 1/4 po X 5/8 po, les rondelles. 4 Répéter l’étape 3 pour chaque coin. 5 Pièces nécessaires.
Installation des tiroirs Insertion des tiroirs. Aligner les glissières Glisser les tiroirs vers l’intérieur Enlèvement des tiroirs.
Installation des armoires de coin Pièces nécessaires. Contre écrou (1/4 po) 1 Remarque : S’assurer d’avoir suffisamment de place pour l’assemblage. Les armoires ne doivent pas être assemblées près des coins d’armoire pour avoir accès à l’arrière des armoires. Sur les bords adjacents, fixer 2 supports à la face intérieure du dessus des coins d’armoire en utilisant les 4 vis #8 de 5/8 po fournies.
Emboîtement des armoires Pièces nécessaires. 1 Positionner une deuxième armoire sur plancher sur le dessus de l’armoire sur plancher existante. 4 X boulons à tête hexagonale (1/4 po x 5/8 po) I 8 X rondelles (1/4 po) 4X contre-écrous (1/4 po) 2 Repérer les trous prépercés sur la surface adjacente et insérer les boulons. 4 Serrer tous les boulons. 10 3 Fixer les armoires à l’aide des boulons à tête hexagonale de 1/4 po x 5/8 po, des rondelles et des écrous fournis.
Installation du palier de support latéral du plan de travail Pièces nécessaires. 2 Support du plan de travail 3 X boulons à tête hexagonale (1/4 po x 5/8 po) 3X rondelles (1/4 po) 3X contre-écrous (1/4 po) 1 Aligner le support. Remarque : Le palier de support est vendu séparément. Un palier de support doit être utilisé si le plan de travail est ajouté à l’ensemble en l’absence d’une deuxième armoire sur plancher/à outils. Ouvrir l’armoire-vestiaire et repérer les trous de chaque côté.
Montage du plan de travail (sur 2 armoires) 1 Placer le plan de travail sur les armoires. 2 Repérer les 2 trous de fixation des deux côtés des armoires. X2 X2 I 3 Percer le plan de travail à l’aide des vis à bois #8 de 5/8 po. Facultatif : Pour le palier de support de l’armoire-vestiaire. X4 Utiliser 2 rondelles et vis à bois #8 de 5/8 po fournies dans l’emballage de l’armoire-vestiaire.
Insertion des étagères d’armoire 1 Relever l’armoire. 2 Insérer l’étagère légèrement en biais. 3 Mettre à niveau l’étagère. 4 Abaisser l’étagère sur des supports en faisant glisser les languettes dans les fentes. 5 S’assurer que l’étagère est bien mise en place. 6 Insérer le reste des étagères.
Assemblage des armoires (cloison sèche et cloison creuse à colombage) 1 Utiliser le localisateur de montants pour repérer les montants et faire une ligne sur le mur avec un crayon. 2 Rassembler les pièces. Vis murale (1/4 po x 2,5 po) Rondelle murale (1/4 po) Armoire murale et armoire-vestiaire : 4 vis murales et 4 rondelles Armoire sur plancher et à outils : 2 vis murales et 2 rondelles 3 Bien appuyer l’armoire contre le mur.
Fixation des armoires sur une paroi à lattes Remarque: Les supports pour les parois à lattes du 3 pouces standard sont vendus séparément. Vérifier auprès de votre fournisseur de parois à lattes pour déterminer la capacité nominale de votre paroi à lattes. NE PAS SURCHARGER. Les supports pour les parois à lattes sont compatibles seulement pour les parois à lattes 3 pouces standard. 1 Pièces nécessaires. Insérer les boulons dans le support de la paroi à lattes.
Raccord des armoires Pièces nécessaires. Remarque : Raccorder les autres armoires à la première armoire solidement assemblée. 1 Aligner les boulons, serrer légèrement. Boulon à tête hexagonale (1/4 po x 5/8 po) Rondelle (1/4 po) Contre-écrou (1/4 po) X4 Remarque : Retirer tous les tiroirs avant de raccorder les armoires ensemble. 2 16 Mettre à niveau les armoires et serrer tous les boulons.
Fixer le cache-néon à l’armoire murale 1 Aligner les trous du cache-néon sur ceux de l’armoire. 3 Vue transversale. 2 Insérer et serrer les boulons et écrous.
Trous d’accès 1 Insérer le passe cable caoutchouc dans le trous a l’interieur de l’armoire. 2 Le trou d’accès permet un branchement facile à la prise de courant. Merci d’avoir acheté un produit NewAge! Si vous avez des questions, veuillez nous appeler ou visiter notre site Web. Appeler au 1.877.306.8930; pour le R.-U., composer le 0800.031.4069; envoyer un courriel à info@newageproducts.com.
IM-PB3.008A-01 72in Pro 72in Bold BOLD AND PRO SERIES 3.0 72IN WALL MOUNTED RACK WARNING: Excessive weight hazard! Use two or more people to move, assemble, or install racking to avoid back injury. Do not leave children unattended near racking. High risk of tipping if racking is installed incorrectly: securely attach racking to the wall to avoid serious injury. For assistance, call 1.877.306.8930; e-mail at info@newageproducts.com.
Index Weight Capacity - 3 Safety Warning - 4 Unpacking - 5 Tools Needed - 5 Spare Parts - 5 Included Quantities - 6 Installation options for Racks - 8 Assembling The Rack - 9 Installing Worktop Side Support Bracket - 16 Installing the Worktop - 17 Installing the Display Shelves - 18 Installing Rack to the Cabinets - 20 Installing multiple Racks - 22 Warranty- 23 2
Weight Capacity 200lbs 150lbs 600lbs 400lbs 600lbs 400lbs 600lbs 400lbs 600lbs Bold 72in Wall Mounted Rack Pro 72in Wall Mounted Rack Total Weight Capacity : 1,300 lbs Max Weight Capacity Per Shelf : 400 lbs Total Weight Capacity : 2,000 lbs Max Weight Capacity per Shelf : 600 lbs Racking must always be wall mounted. Racking must always be wall mounted.
Safety Warning PLEASE READ THIS FIRST 1. Pro Wall Mounted Racks have a rated total load capacity of 2,000 pounds, evenly distributed, using 3” lag bolts anchored into solid wood studs. 2. Bold Wall Mounted Racks have a rated total load capacity of 1,300 pounds, evenly distributed, using 3” lag bolts anchored into solid wood studs. 3. Do not load more than the recommended weight capacity per shelf. Live loads (people,pets, etc.
Unpacking • Begin by placing the package on a covered flat surface. • Remove all cardboard, foam packaging material and clear plastic bags. • Dispose / recycle all packaging materials. • Verify all the contents in the box and gather the required tools. See “Parts” and “Tools Needed” in the list below.
Included Quantities Bold 72in Wall Mounted Rack ITEM NO. PartNo DESCRIPTION QTY. 1 H00002A-01 M6 Flat Washer 23 2 H00009A-01 M6x75mm Hex Head Tapping Screw 9 3 H00043A-01 0.25-20x0.625in Hex Bolt 12 4 H00055A-01W Nut 0.25 Inch lock nut 2 5 H00075A-01 #8 x 5/8” Wood Screw 2 6 PB3-19.008A-01-XX Worktop Support Bracket 1 7 PB3-27.001A-01-XX B3 72in Rack Side Panel 2 8 PB3-27.002A-01-XX B3 72in Rack Frame Bottom Front 1 9 PB3-27.
Included Quantities Pro 72in Wall Mounted Rack ITEM NO. PartNo DESCRIPTION QTY. 1 H00002A-01 M6 Flat Washer 23 2 H00009A-01 M6x75mm Hex Head Tapping Screw 9 3 H00043A-01 0.25-20x0.625in Hex Bolt 12 4 H00055A-01 Nut 0.25 Inch lock nut 2 5 H00075A-01 #8 x 5/8” Wood Screw 2 6 PB3-19.008A-01-XX Worktop Support Bracket 1 7 PB3-28.001A-01-XX P3 72in Rack Side Panel 2 8 PB3-27.002A-01-XX B3 72in Rack Frame Bottom Front 1 9 PB3-27.
Installation options for Racks 1 Single 72in Wall Mounted Rack Install. See full instructions on pages 9-15. 3 72in Wall Mounted Rack installed with NewAge Cabinets. See full instructions on pages 20 & 21. Note: • Prior to install, ensure you have planned your wall space carefully and wall studs have been located. • Consider the location of electrical outlets when planning layout. 2 72in Wall Mounted Rack installed with NewAge Display Shelves and Worktop.
Assembling The Rack Parts required 9 x Hex Head Tapping Screw 3 x Rack Hanging Bracket 1 x Cordless Power Drill 2 23 X Washer 1 x Adjustable wrench 1 Remove all items from packaging and ensure all parts have been provided. 3 Take Item 9 and align it to the bottom slots and hole. Make sure the two holes at the bottom of the beam are facing you as shown in image below. 12 X Hex Bolt 1 x Socket driver wrench Start by placing the left side panel on its side (Item 7).
Assembling The Rack (Contd.) 6 Using the opposite side panel (Item 7), follow steps 2 to 5 to secure the panel to the back beams. 73 Carefully stand the rack up and attach the top shelf (Item 12). 7 8 12 Secure the top shelf to the side panels using a bolt (Item 3) and a washer (Item 1) at all four corners. A 9 A B A A Secure the top shelf to the back beam using a bolt (Item 3) and a washer (Item 1) A B 3 1 B 3 10 1 Attach the front bottom beam (Item 8) to the side panels.
Assembling The Rack (Contd.) 12 Using a stud finder, locate and mark the center position of the studs on the wall. Ensure they fit the size of your install. Mark a line 4 inches above the floor and another line 71.8in (If installing the bold 72in Wide Rack) or 79.8in (If installing the Pro 72in Wide Rack) on the wall. 68.75” Bold : 71.8 in Pro: 79.8 in 16in or. 24in Note: Install the 3 wall hanging brackets over a span of 68.75in as equally as possible on studs.
Assembling The Rack (Contd.) 15 Attach the wall mounting brackets to the studded wall with a M6 Flat washer(Item 1) and Hex Head Tapping screw (Item 2). 2 1 16 Carefully lift the rack, move towards the wall and slide it down to hang on the wall hanging brackets. Note: It is recommended for two people to lift the wall mounted rack to position.
Assembling The Rack (Contd.) 17 Mark three holes of the back bottom beam equidistantly. Make sure the marked holes will be hitting a stud. Once the holes have been marked, drill pilot holes using a 3/16” drill bit on the studded wall. Pilot hole must bore into 3 inches of solid wood for lag screw to be fully secured. D D 18 Secure the bottom beam to the wall with a tapping screw and a washer.
Assembling The Rack (Contd.) 19 Once the rack has been secured to the wall, attach a back beam(Item 10) to the side panels by sliding it into the grooves at both the corners. 20 Continue to do so for the remaining back beams. If installing the Pro Rack, assemble 3 back beams. If installing the Bold Rack, assemble 2 back beams. 10 10 Front Back 21 Following steps 1 to 2, attach the front beams (Item 10) to the side panels by sliding it into the grooves at both the corners.
Assembling The Rack (Contd.) 22 Install the wire grids (Item 13) on the top, center and the bottom beams.
Installing Worktop Side Support Bracket 1 Parts required 2 1 x Support bracket 2 X Hex Bolt (1/4” x 5/8”) 4 X Washer (1/4”) 2 X Lock Nut (1/4”) Align support bracket (Item 6) with the holes. 3 Locate holes on the side panel of the rack. Fasten lock nuts (Item 4), bolts (Item 3), and washers (Item 1). X2 6 4 4 16 Level the support bracket using a Magnetic leveler. 5 1 3 Tighten the nut and bolt using a spanner.
Installing the Worktop 1 Parts required Install two racks one adjacent to the other with a distance “L (Length of the worktop)“ to install worktop between the two. L 1 x Worktop 2 X Washer (1/4”) 2 2x Wood Screws 1 x Cordless Power Drill Place the worktop between the two racks resting on the side support brackets. Mark holes of the side support brackets on the worktop at all corners. 3 Drill into the worktop using #8 x 5/8” Wood Screws and washers on both sides.
Installing the Display Shelves 1 Parts required 8 X Washer (1/4”) 2 L 4 X Hex Bolt (1/4” x 5/8”) 2 X NewAge Bold / Pro Display Shelf Install two racks adjacent to each other on wall with a distance “L (Length of the display shelf )“ to install Display shelves between the two. 4 X Lock Nut (1/4”) Identify the holes “A” on top of the side panels for the both racks. 3 Take the top display shelf and identify the front holes “B” on both sides.
Installing the Display Shelves (Contd.) 5 Secure the top display shelf to the racks by using a bolt, lock nut and washers at the aligned holes on both sides. 7 Level the shelves using a Magnetic leveler and tighten the bolts using a spanner on both sides. 6 Repeat steps 2 to 5 for installing the bottom display shelf.
Installing Rack to the Cabinets The Bold and Pro Wall Mounted Rack`s have been designed to be an off the floor and wall mounted solution. Do not install the Wall Mounted Racks to floor mounted cabinets. 1 Parts required 8 X Washer (1/4”) Install cabinet on the wall. 4 X Hex Bolt (1/4” x 5/8”) 4 X Lock Nut (1/4”) 2 20 Install rack next to the cabinet such that the top of the cabinet aligns properly with the top of the rack.
Installing Rack to the Cabinets (Contd.) 4 Identify the holes on the rack aligned with the cabinet. 5 Open the cabinet door and install bolt, lock nut and washers at all the aligned holes to attach rack with the cabinet.
Installing multiple Racks Parts required 8 X Washer (1/4”) 1 Install two racks on the wall with the top surfaces flush and aligned. 3 Attach racks using a bolt, lock nut and washers. 4 X Hex Bolt (1/4” x 5/8”) 4 X Lock Nut (1/4”) 2 Identify aligned holes on the side panels and insert bolts.
Warranty When this product is installed, operated and maintained according to the instructions attached to or furnished with the product, NewAge Products Inc. will replace the defective product or parts if the part fails as a result of defective materials or workmanship for the Lifetime of the product. NEWAGE PRODUCTS INC. WILL NOT PAY FOR: 1. Service calls to correct the installation of any NewAge products or to instruct you how to use or install them. 2.
IM-PB3.008A-01 72po Pro 72po Bold SÉRIE 3.0 BOLD ET PRO 72 PO SUPPORT MURAL ÉTAGÈRE AVERTISSEMENT: Risque de poids excessif! Utilisez deux personnes ou plus pour déplacer, assembler ou installer l’étagère murale afin d’éviter toute blessure au dos ou autre. Ne laissez pas les enfants sans surveillance près de l’étagère murale. Risque élevé de chute d’objets si l’étagère murale est mal installée: elle doit être installée de manière sûre pour éviter des blessures graves.
Index Capacité de charge - 3 Avertissements de Sécurité - 4 Déballage - 5 Outils Requis- 5 Pieces de rechange- 5 Quantités Incluses- 6 Options d’installation pour les étagères- 8 Assemblage de l’étagère- 9 Installation du support latéral de plan de travail - 16 Installation du plan de travail- 17 Installation des présentoirs - 18 Installation d’un étagère sur les armoires - 20 Installation de plusieurs étagères - 22 Garantie à vie limitée du fabricant- 23 2
Capacité de charge 200lbs 150lbs 600lbs 400lbs 600lbs 400lbs 600lbs 400lbs 600lbs Étagère murale Bold de 72 po Étagère murale Pro de 72 po Capacité de charge totale : 1,300 lb Capacité de charge max. par tablette : 400 lb Capacité de charge totale : 2,000 lb Capacité de charge max. par tablette : 600 lb Les étagères doivent toujours être fixées au mur Les étagères doivent toujours être fixées au mur.
Avertissements de sécurité PRIÈRE DE COMMENCER PAR LIRE CECI 1. Les étagères murales Pro disposent d’une capacité de charge nominale totale de 2 000 livres, distribuée de façon égale, grâce à l’utilisation de tire-fonds de 3 po ancrés dans des montants de bois massif. 2. Les étagères murales Bold disposent d’une capacité de charge nominale totale de 1 300 livres, distribuée de façon égale, grâce à l’utilisation de tire-fonds de 3 po ancrés dans des montants de bois massif. 3.
Déballage • • • • Commencer par placer l’emballage sur une surface plane couverte. Retirer tout le carton, les matériaux d’emballage en mousse et les sacs en plastique transparents Mettre au rebut/recycler tous les matériaux d’emballage. Vérifier l’ensemble du contenu de la boîte et réunir les outils nécessaires. Voir les « Pièces » et « Outils requis » dans la liste ci-dessous.
Quantités Incluses Bold 72po Support Mural Étagère ITEM NO. PartNo LA DESCRIPTION QTY. 1 H00002A-01 M6 Rondelle Plate 23 2 H00009A-01 M6x75mm Vis autotaraudeuse à tête hex 9 3 H00043A-01 0,25-20 x 0,625po Boulon à tête hex 12 4 H00055A-01W contre-écrou 0,25 ouce 2 5 H00075A-01 #8 x 5/8” Vis à bois 2 6 PB3-19.008A-01-XX Support du plan de travail 1 7 PB3-27.001A-01-XX B3 72po Panneau latéral 2 8 PB3-27.002A-01-XX B3 72po cadre inférieur avant 1 9 PB3-27.
Quantités Incluses Pro 72po Support Mural Étagère ITEM NO. PartNo LA DESCRIPTION QTY. 1 H00002A-01 M6 Rondelle Plate 23 2 H00009A-01 M6x75mm Vis autotaraudeuse à tête hex 9 3 H00043A-01 0,25-20 x 0,625po Boulon à tête hex 12 4 H00055A-01 contre-écrou 0,25 ouce 2 5 H00075A-01 #8 x 5/8” Vis à bois 2 6 PB3-19.008A-01-XX Support du plan de travail 1 7 PB3-28.001A-01-XX P3 72po Panneau latéral 2 8 PB3-27.002A-01-XX B3 72po cadre inférieur avant 1 9 PB3-27.
Options d’installation pour les étagères 1 Remarque: • Avant l’installation, s’assurer d’avoir bien planifié l’espace mural et repéré l’emplacement des montants. • Lors de la planification de la disposition, s’assurer de prendre en compte l’emplacement des prises électriques. 2 4 8 Étagère murale de 72 po installée avec des présentoirs et un plan de travail NewAge. Il est possible d’installer un plan de travail et des présentoirs de façon indépendante. Voir les instructions complètes aux pages 16-19.
Assemblage de l’étagère 1 Pièces requises 3 x Support mural 9 x Vis autotaraudeuses à tête hex 1 x Perceuse sans fil 2 23 X Rondelle 1 x Clé à molette Retirer tous les articles de l’emballage et s’assurer que tous les éléments y sont. 12 X Boulons Hex 1 x Clé à douille Commencer par placer le panneau gauche sur le côté (article 7). S’assurer que les 2 trous inférieurs vous font face. 3 Prendre l’article 9 et l’aligner avec le trou et les fentes inférieures.
Assemblage de l’étagère (suite) 6 En utilisant le panneau latéral opposé (article 7), suivre les étapes 2 à 5 pour fixer le panneau aux montants arrière. 73 Soulever prudemment l’étagère et fixer la tablette supérieure (article 12). 7 8 12 Fixer la tablette supérieure aux panneaux latéraux en utilisant un boulon (article 3) et une rondelle (article 1) aux quatre coins.
Assemblage de l’étagère (suite) 12 À l’aide d’un détecteur de montant, repérer et marquer la position centrale des montants sur le mur. S’assurer qu’ils sont adéquats pour la taille de votre installation. Marquer une ligne de 4 pouces au-dessus du plancher et une autre à 71,8 po (dans le cas de l’installation d’une étagère de 72 po Bold) ou à 79,8 po (dans le cas de l’installation d’une étagère de 72 po Pro) sur le mur. 68.75 po Bold : 71, 8 po Pro: 79, 8 po 16 po ou.
Assemblage de l’étagère (suite) 15 Fixer les supports de montage mural sur la cloison creuse à colombage avec une rondelle plate M6 (article 1) et une vis autotaraudeuse à tête hex. (article 2). 2 1 16 Soulever délicatement l’étagère, la déplacer vers le mur et la glisser pour procéder à l’installation avec les supports muraux. Remarque : Il est recommandé que deux personnes soulèvent l’étagère murale pour la positionner.
Assemblage de l’étagère (suite) 17 Marquer trois trous de façon équidistante sur le montant inférieur arrière. S’assurer que les trous marqués se trouveront vis-à-vis d’un montant. Une fois que les trous ont été marqués, percer des avant-trous en utilisant un foret de 3/16 po sur la cloison creuse à colombage. L’avant-trou doit s’enfoncer dans 3 pouces de bois massif pour que le tire-fond soit solidement fixé. D D 18 Fixer le montant inférieur au mur avec une vis autotaraudeuse et une rondelle.
Assemblage de l’étagère (suite) 19 Une fois que l’étagère a été fixée au mur, fixer un montant arrière (article 10) aux panneaux latéraux en les faisant glisser dans les rainures se trouvant aux deux coins. 20 Procéder de la même façon pour les montants arrière restants. Pour l’installation d’une étagère Pro, assembler 3 montants arrière. Pour l’installation d’une étagère Bold, assembler 2 montants arrière.
Assemblage de l’étagère (suite) 22 Poser les grilles métalliques (article 13) sur les montants supérieur, central et inférieur.
Installation du support latéral de plan de travail : 1 Pièces requises 1 x Brides de soutien 4 X Rondelles (1/4 po) 2 Repérer les trous sur le panneau latéral de l’étagère. 2 x Boulon à tête hex. (1/4 po x 5/8 po) 2 x Contre-écrous (1/4 po) Aligner les brides de soutien (article 6) avec les trous. 3 Fixer les contre-écrous (article 4), les boulons (article 3) et les rondelles (article 1). X2 6 4 4 16 Mettre au niveau la bride de maintien à l’aide de l’indicateur magnétique de niveau.
Installation du plan de travail 1 Pièces requises Installer deux étagères de façon adjacente en utilisant une distance « L (Longueur du plan de travail) » pour poser le plan de travail entre les deux. L 1 x Plan de travail 2 x Vis à bois 2 X Rondelles (1/4 po) 1 x Perceuse sans fil 2 Placer le plan de travail entre les deux étagères avec les deux brides latérales de soutien. Marquer les trous des brides latérales de soutien sur tous les coins du plan de travail.
Installation des présentoirs 1 Pièces requises 8 X Rondelles (1/4 po) 2 L 4 X Boulons à tête hex. (1/4 po x 5/8 po) 2 X Présentoirs NewAge Bold/Pro Poser deux étagères de façon adjacente Sur le mur en utilisant une distance « L (Longueur du présentoir) pour installer les présentoirs entre les deux. 4 X Contre-écrous (1/4 po) identifier les trous « A » sur le haut des panneaux latéraux pour les deux étagères. 3 Prendre le présentoir supérieur et identifier les trous avant « B » de chaque côté.
Installation des présentoirs (suite) 5 Fixer le présentoir supérieur sur les étagères en utilisant un boulon, un contreécrou et des rondelles au niveau des trous alignés des deux côtés. 7 Mettre les étagères au niveau en utilisant un indicateur magnétique de niveau et serrer les boulons en utilisant une clé à molette des deux côtés. 6 Répéter les étapes 2 à 5 pour l’installation du présentoir.
Installation d’un étagère sur les Les supports muraux Bold et Pro ont été conçus pour être une solution murale ou au sol. N’installez pas les racks muraux dans des armoires montées au sol. 1 Pièces requises 8 X Rondelles (1/4 po) Installation d’une armoire sur le mur. 4 X Boulons à tête hex. (1/4 po x 5/8 po) 4 X Contre-écrous (1/4 po) 2 20 Installer une étagère à côté de l’armoire de manière à ce que le haut de l’armoire s’aligne correctement avec le haut de l’étagère.
Installation d’un étagère sur les armoires (suite) 4 Identifier les trous sur l’étagère alignée avec l’armoire. 5 Ouvrir la porte d’armoire et poser un boulon, un écrou et des rondelles au niveau de tous les trous pour fixer l’étagère avec l’armoire.
Installation de plusieurs étagères Pièces requises 8 X Washer (1/4”) 1 Poser les deux supports sur le mur, fixés et parfaitement alignés l’un avec l’autre. 3 Fixer les deux supports en utilisant un boulon, un contre-écrou et des rondelles. 4 X Hex Bolt (1/4” x 5/8”) 4 X Lock Nut (1/4”) 2 Identifier les trous alignés sur les panneaux latéraux et insérer les boulons.
Garantie à vie limitée du fabricant Lorsque ce produit est installé, utilisé et entretenu conformément aux instructions ci-jointes ou fournies avec le produit, NewAge Products Inc. remplacera les pièces ou le produit défectueux advenant que ceux-ci découlent d’un défaut de matériel ou de fabrication pendant la durée de vie du produit. NEWAGE PRODUCTS INC. N’ASSUMERA PAS LES COÛTS SUIVANTS : 1.
IM-PB3.06A-01 Bold 3.0 Performance 2.0 Project Centre ! WARNING: Excessive weight hazard! Use two or more people to move, assemble, or install cabinets and locker to avoid back injury. Do not leave children unattended near cabinets. High risk of tipping if cabinets are installed incorrectly: securely attach cabinets to the wall to avoid serious injury. For assistance, call 1.877.306.8930; for U.K 0800.031.4069; e-mail at info@newageproducts.com.
Index Index/ Guidelines and Weight Capacity Parts Supplied Tools Needed Warranty Side Handle Installation Attaching Casters Installing Door and Drawer Handles Removing and Inserting Drawers Attaching Worktop to Cabinets Installing Shelves 2 3 3 4 5 6 7 8 9 10 Unpacking • Remove all cardboard, foam packaging material and clear plastic bags. • Dispose / recycle all packaging materials. • Verify all the contents in the box and gather the required tools. See “Parts” and “Tools Needed” in the list below.
Parts Supplied Bold 3.0 Project Center Performance 2.
Manufacturer Warranty Limited Lifetime When this product is installed, operated and maintained according to the instructions attached to or furnished with the product, NewAge Products Inc. will replace the defective product or parts if the part fails as a result of defective materials or workmanship for the Lifetime of the product. NEWAGE PRODUCTS INC. WILL NOT PAY FOR: 1. Service calls to correct the installation of any NewAge products or to instruct you how to use or install them. 2.
Installing Side Handle 1 Parts Needed. 4 X Hex Bolt (1/4” x 5/8”) Determine which side to install the side handle, the side handle should be installed on the same side as the casters with brakes. Side Handle 4 X Washer (1/4”) 2 Align handle holes with holes on side of cabinet. Insert and tighten 1/4 inch bolts and washers. www.newageproducts.
Installing Casters 1 Parts Needed. 16 X Hex Bolt (1/4” x 5/8”) 4in Casters 16 X Washer (1/4”) 16 X Spring (1/4”) 2 Note: Locking casters should be installed on same end as side handle. Flip cabinet upside down, locate holes forming a square. 3 Open cabinet, remove any shelves or loose items. Close and lock doors and drawers. Align caster holes and bolts to cabinet using 4 Hex bolts, 4 spring washers and 4 (1/4”) washers per caster.
Installing Handles (for Performance 2.0 series) 1 Parts Needed. 8 “ Door Handle Align Handle to holes on doors and drawers. Handle Bolt (M4 x 30mm) 12 “ Drawer Handle 2 Screw in bolts using #2 Philips head screwdriver being careful not to overtighten bolts. www.newageproducts.
Installing the Drawers Removing Drawers. Right Side Left Side Slide Out Inserting Drawers. Align Rails 8 Slide In www.newageproducts.
Mounting the Worktop 1 Parts needed. 6 x Wood Screw (#8 x 5/8”) Note: Please Ensure that casters are locked in place before installing the worktop Remove the top 2 drawers and open the doors. See page 8. 1 x Cordless Power Drill 1 x #2 Phillips Bit 2 Align worktop to the front, the back or leave a 1in overhang on the front and back 3 Place worktop on cabinet. Locate (6 ) punch holes on inside of cabinet. Pre-drill 3mm (1/8”) pilot holes in worktop.
Inserting Cabinet Shelves 1 Open doors. 2 Insert shelf at a slight angle. 3 Level shelf. 4 Lower shelf onto brackets by sliding tabs into slots. 5 Ensure shelf is clipped in position. 6 Thank you for purchasing a NewAge Product! Please give us a call or visit online if you have any questions. Call 1.877.306.8930; for UK 0800.031.4069; e-mail at info@newageproducts.com www.newageproducts.
IM-PB3.06A-01 Série Bold 3.0 Série Performance 2.0 Poste De Travail ! AVERTISSEMENT: RISQUE DE POIDS EXCESSIF! Déplacer, assembler ou installer les armoires et armoires-vestiaires avec l’aide de deux personnes ou plus. Dans le cas contraire, il pourrait en découler des blessures au dos ou autre. Ne pas laisser les enfants sans surveillance près des armoires.
Index Index / Capacités de poides Pièces fournies Outils nécessaires Garantie Installation de la poignée latéral Installation des roulettes Installation des tiroirs et poignees de portes Installation des poignees de tiroirs Montage du plan de travail Insertion des étagères d”armoire 2 3 3 4 5 6 7 8 9 10 Déballage • Commencer par placer la boîte sur une surface plate recouverte. • Retirer tout le carton, le matériel d’emballage en mousse et les sacs en plastique transparent.
Pièces fournies Bold 3.0 Poste de Travail Performance 2.
Garantie à vie limitée du fabricant Lorsque ce produit est installé, utilisé et entretenu conformément aux instructions ci-jointes ou fournies avec le produit, NewAge Products Inc. remplacera les pièces ou le produit défectueux advenant que ceux-ci découlent d’un défaut de matériel ou de fabrication pendant la durée de vie du produit. NEWAGE PRODUCTS INC. N’ASSUMERA PAS LES COÛTS SUIVANTS : 1.
Installation de la poignée latéral 1 Pièces nécessaires. 4 X Hex Bolt (1/4” x 5/8”) Déterminez de quel côté installer la poignée latérale, la poignée latérale doit être installée du même côté que les roulettes avec freins. Poignée latéral 4 X Rondelles (1/4”) 2 Alignez les trous de la poignée avec les trous sur le côté de l’armoire. Insérer et serrer les boulons et les rondelles de 1/4 po. www.newageproducts.
Installation des roulettes Remarque: Les roulettes de verrouillage doivent être installées sur la même extrémité que la poignée 1 Pièces nécessaires. 4 x roulettes 16 X rondelles (1/4 po) 2 Ouvrir l’armoire et retirer les étagères ou les objets au fond. Fermez et verrouillez les portes et les tiroirs. 16 X boulons à tête hexagonale (1/4 po x 5/8 po) 16 X Rondelle d’arrêt à resort (1/4 po) Retourner l’armoire et repérer les trous formant un carré.
Installation des poignées (pour série Performance 2.0) 1 Pièces nécessaires. Poignées 8 po 2 Alignez la poignée avec les trous des portes et des tiroirs. Boulons pour poignées Poignées 12 po 3 Visser les boulons à l’aide du tournevis cruciforme n ° 2 en veillant à ne pas trop serrer les boulons. www.newageproducts.
Installation des tiroirs Enlèvement des tiroirs. Côté droit Côté gauche Glisser les tiroirs vers l’extérieur Insertion des tiroirs. Aligner les glissières 8 Glisser les tiroirs vers l’intérieur www.newageproducts.
Montage du plan de travail 1 6 x Vis a bois (#8 x 5/8”) To u r n e v i s c r u c i fo r m e #2 3 2 Pièces nécessaires. REMARQUE: Veuillez vous assurer que les roulettes sont bien verrouillées avant d’installer le plan de travail Retirez les 2 tiroirs supérieurs et ouvrez les portes. Voir page 8. Perceuse mecanique sans fil Aligner le plan de travail vers l’avant, l’arrière ou laisser un surplomb de 1 po à l’avant et à l’arrière 4 Placez le plan de travail sur l’armoire.
Insertion des étagères 1 Ouvrez les portes de l’armoire 2 Incline et insérer l’étagère légèrement. 3 Mettre à niveau l’étagère. 4 Abaisser l’étagère sur des supports en faisant glisser les languettes dans les fentes. 5 S’assurer que l’étagère est bien mise en place. 6 Merci d’avoir acheté un produit NewAge! Si vous avez des questions, veuillez nous appeler ou visiter notre site Web. Appeler au 1.877.306.8930; pour le R.-U., composer le 0800.031.4069; envoyer un courriel à info@newageproducts.