Owner's Manual

MT-106
[RS6F51H]
INPUT SHAFT AND GEARS
Be sure not to hook the ends of the 2 spread springs (front
and back have two each) on the same shifting insert.
13. Install the 5th-6th synchronizer hub assembly using Tool as
shown.
CAUTION:
Align the grooves of the 5th-6th shifting insert and 5th-6th
baulk ring.
14. Install the needle bearing, 6th input gear and then 6th bushing
using Tool as shown.
15. Install the snap ring onto the input shaft, and measure to check
that end play (gap between snap ring and groove) of the 6th
bushing is within specification.
If the measurement is outside the standard value, select the
appropriate size snap ring.
Snap Rings
SCIA1083E
SCIA1039E
SCIA1040E
End play standard value : 0 - 0.1 mm (0 - 0.004 in)
SCIA0970E
Thickness Part number Thickness Part number
1.76 mm (0.0693 in)
1.81 mm (0.0713 in)
1.86 mm (0.0732 in)
1.91 mm (0.0752 in)
1.96 mm (0.0772 in)
32204 8H511
32204 8H512
32204 8H513
32204 8H514
32204 8H515
2.01 mm (0.0791 in)
2.06 mm (0.0811 in)
2.11 mm (0.0831 in)
2.16 mm (0.0850 in)
2.21 mm (0.0871 in)
32204 8H516
32204 8H517
32204 8H518
32204 8H519
32204 8H520