User Manual
Installation 3-3
6. When the four shipping brackets have been removed, slide the forklift forks under the front
of the coating system between the levelers (feet). Use the forklift to gently lift the coating
system off of the crate.
NOTE You may use the shipping crate for future shipping purposes or dispose of
according to local regulations. Save the shipping brackets. They can be used
later for seismically securing the coating system. See 3.9 Anchoring the
Coating System or Facility Specification SL94XE (P/N 7218847).
7. Move the coating system over the location where it will be installed
8.
Slowly lower the forklift until the coating system conveyor rail is at the approximate height
of the mating upstream and downstream equipment.
9.
Raise or lower each leveler (foot) as follows until they all touch the floor:
a. Loosen the 1 ½ inch lock nut on the leveler. See Figure 3-2.
b. Adjust the 1 ½ inch post nut to raise or lower each leveler as required.
Turning the post nut clockwise lowers the leveler. Turning the post nut
counterclockwise raises the leveler.
c. Tighten the lock nut.
Item Description Item Description
1 Post 4 Post Nut
2 1 1/2-inch Wrench 5 Lock Nut
3 Leveler (foot)
Figure 3-2 Adjusting the Levelers
10. Remove bag and plastic wrap from the machine.
NOTE Location of packaging materials to be removed is indicated by the presence of
red warning tags.
11. Remove all shrink-wrap and other packing material from the perimeter of the coating
system.
12. Remove all perimeter packaging material from the dispensing area.
NOTE Remove all shrink wrap and packing foam from the system prior to moving it
to a clean room. If necessary, clean the system thoroughly.
1
2
3
4
5