Installation Procedure(ex. @Garage)
Necessary Tool
6
Push the "⑫Flex Feeder" into the tip of the "③Flex Pipe 2"".
Flex Pipe 2"
Flex Feeder
7
Insert the "
③Flex Pipe 2"
" into the "⑥Base Junction Support" until you touch the inside
of the rain cap on the roof.
With the "
③Flex Pipe 2"
" fully inserted into the vent, make a mark at the "⑥Base
Junction Support" so you can check for movement during the rest of installation.
Marker
Step-1
(Work where equipment is installed)
Install the "
⑫
Flex Feeder" always, even in the case of straight B-Vent runs.
("
⑫
Flex Feeder" prevents debris from falling into the "③Flex Pipe 2"".)
Be sure to do
When pushing "③Flex Pipe 2"" through the B-Vent, if there is unusual feeling
(touching the bump of screw, etc.), do not continue to push in and stop the installation.
Be sure to do
Do not use the "③Flex Pipe 2"" at any jobsite with vent runs longer than 35', do
not join two shorter flex pipes together even if the run is less than 35'.
Prohibited
Point
Before inserting, try to straighten curl of the tip of
"
③Flex Pipe 2"
"
as much as possible.
However, when doing so, bending radius should be more than 7 inch.
Point
Continue to push
"
③Flex Pipe 2"
"
strongly until the end and make sure that it does not
stop in the middle.
r>7 inch