Communication Server Large System Installation and Commissioning
Page 335 of 456
Communication Server 1000M and Meridian 1 Large System Installation and Commissioning
342
Performing acceptance tests
Contents
This section contains information on the following topics:
Acceptance tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 335
Testing the module power supply . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 336
Testing the blower unit and thermal sensor . . . . . . . . . . . . . . . . . . . . . 337
Testing the sysload . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 339
Testing the system terminal and system monitor . . . . . . . . . . . . . . . . . 340
Testing the PFTU . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 341
Acceptance tests
Perform the following acceptance tests after the system loading is completed.
1 “Testing the module power supply” on page 336
2 “Testing the blower unit and thermal sensor” on page 337
3 “Testing the sysload” on page 339
4 “Testing the system terminal and system monitor” on page 340
5 “Testing the PFTU” on page 341
CAUTION
Ensure that the current DEP Lists are installed.