Page 34 of 456 Introduction
NN43021-310 Standard 02.01 December 2007
11 Connect a system terminal (or modem); go to “Connecting a system
terminal or modem” on page 171.
12 Install cabling:
To cable Common Equipment, go to “Cabling Common Equipment
in a Single Group system” on page 187.
To cable network loops, go to “Cabling network modules and loops”
on page 239.
To cable IPE Modules to the MDF and to connect lines and trunks,
go to “Cabling lines and trunks” on page 261.
13 Power up the system and load the system software; go to “Powering up
the system and initial loading” on page 299.
Note: If you are upgrading your system, do not install new software.
Instead, return to the upgrade procedures provided in Communication
Server 1000M and Meridian 1 Large System Upgrade NTPs
(NN43021-458 – NN43021-475).
14 Perform acceptance tests; go to “Performing acceptance tests” on
page 335.
15 To test circuit cards, see “Acceptance tests” in Circuit Card: Description
and Installation (NN43001-311). To test telephones and attendant
consoles, see Telephones and Consoles: Description, Installation, and
Operation (NN43001-567).
16 Replace all covers and grills on the front and rear of the system.