READY FOR INPUT
4 Step through the keys on the keyboard one at a time. All keyboard input
should be echoed until END is entered.
5 Exit LD 37:
****
End of Procedure
Testing the PFTU
Use Procedure 63 to test a PFTU and its interface with the system monitor.
Procedure 63
Testing the PFTU and its interface
1 Set the line transfer switch on the PFTU to BYPASS. Associated
attendant consoles should display a major alarm.
2 Set the line transfer switch on the PFTU to NORMAL.
3 Set the line transfer switch on the attendant console associated with the
PFTU to ON. Associated attendant consoles should display a major
alarm.
4 Set the line transfer switch on the attendant console associated with the
PFTU to OFF. The “major” alarm condition displayed on attendant
consoles associated with the PFTU should disappear.
5 Repeat step 2 and step 3 for each attendant console associated with the
PFTU.
6 Set the line transfer switch on the PFTU to BYPASS and test the
telephones and trunks connected to the PFTU.
Place an outgoing call from each telephone associated with the
PFTU. Each telephone should be connected directly to a trunk.
Place an incoming call on each trunk associated with the PFTU. Each
trunk should be connected directly to a telephone.