76
Positioning and leveling equipment
Contents
This section contains information on the following topic:
Positioning and leveling the equipment . . . . . . . . . . . . . . . . . . . . . . . . 71
Positioning and leveling the equipment
Columns normally stand on adjustable feet that provide leveling capability
and ground isolation. However, casters are available and can be used for
two-tier columns. If a third module is added to a column with casters, the
casters must be replaced with leveling feet.
Note: If earthquake bracing is required, go to “Installing earthquake
bracing” on page 343 to install column and floor bracing, and to position
and level equipment. When those procedures are complete, return to
Step 4 or Step 5 (as applicable) in the initial installation procedure.
Use Procedure 3 to position and level the equipment.
Procedure 3
Positioning and leveling the equipment
1 Check the equipment room floor plan to position columns.
2 Level the column.
a. Remove the front and rear exhaust grills.
b. Remove the front and rear air intake grills.