Installation Instructions

14
• Position the starter strip’s flange underneath the furring strips and assure a
perfect level before you fasten the strip at every furring strip. Attach with #8
or #10 corrosion resistant screws. The screws must penetrate at least 1 1/4”
(32mm) into the perimeter joists or into the studs.
Installing the SV-Starter and Furring Strips
Adjust to hide
foundation line
• Measure and mark each corner where you want the first row of Novabrik to
start. We usually mark each corner at 1/2” (13mm) above the foundation.
• Hold the string straight and tight at both ends and snap the line on the house
wrap.
• Line up the furring strips over the framing studs and above the chalk line.
Attach with # 8 or # 10 corrosion resistant screws at 10” (250mm) c/c. The
screws must penetrate at least 1 1/4” (32mm) into the studs.
NOTE: Do not screw the furring strips at elevation 0”, they will be
screwed into studs when anchoring the starter strip.