DESCRIPTION OF THE PARAMETERS 
PV / SP indication - The upper display shows the 
current value of PV. The lower display shows the 
control SP value. 
avto
Control 
Control Mode: 
Yes
 - Means automatic control mode.
no
 - Means manual control mode. 
Bumpless transfer between automatic and manual. 
PV / MV- The upper display shows PV value and the 
lower display shows the percentage 
of the 
manipulated  variable  MV 
applied to the control 
output.  
When in manual control, the MV 
value can be 
manually changed by the 
and 
 keys.
When in 
auto mode the MV value can only be viewed. 
To distinguish the MV display from the SP display, 
the MV is shown flashing intermittently. 
Pr n 
Enable 
Program 
Execution of Program - Selects the ramp and 
soak profile program to be executed.  
  0 -  does not execute program 
  1 to 7 -  number of the program to be   
      executed  
With enabled outputs (
RvN
 = 
YES
), the program 
starts right after the program is selected. 
rvn
Enables control outputs and alarms. 
YES
  - Outputs enables. 
NO
    - Outputs not enabled. 
CYCLE OF TUNING 
Atvn 
Auto-tune 
Enables the auto tuning  feature for the PID 
parameters.  
YES
 – Auto-tune enable 
NO
  – Do not execute auto tune. 
See the DETERMINATION OF PID PARAMETERS 
section for more details. 
pb 
Proportional 
Band 
Proportional Band - Value of the term P of the 
control mode PID, in percentage of the maximum 
span of the input type. Adjust of between 0 and 
500.0 %. 
Select zero for ON/OFF control. 
ir 
Integral Rate 
Integral  Rate  -  Value of the term I  of the PID 
algorithm, in repetitions per minute  (Reset). 
Adjustable between 0 and 24.00. 
Displayed only if proportional band≠ 0. 
dt 
Derivative Time 
Derivative Time - Value of the term D of the control 
mode PID, in seconds. Adjustable between 0 
and250seconds. 
Displayed only if proportional band≠ 0. 
(t 
Cycle Time 
Pulse Width Modulation (PWM) period in seconds. 
Adjustable between 0.5 and 100.0 seconds. 
Displayed only if proportional band≠ 0. 
kyst 
Hysteresis 
Control hysteresis - This parameter is only shown 
for ON / OFF control. Adjustable between 0 and 
the measurement input type span. 
Displayed only if proportional band = 0. 
ACt 
Action 
Control logic: 
re
Control with reverse Action. Appropriate for 
heating. Turns control output on when PV is 
below SP. 
dir
Control with direct Action. Appropriate for 
cooling
. Turns control output on when PV is 
above SP. 
bias
Bias function - Allows adding a percentage value 
between -100 % and +100 %. to the MV control 
output. 
The value 0 (zero) disables the function. 
ovll 
Output Low 
Limit 
Lower limit for the control output -  Minimum 
percentage value assumed by the control output 
when in automatic mode and in PID.  
Typically configured with 0.0 %. 
ovkl 
Output High 
Limit 
Upper limit for the control output -  Maximum 
percentage for the control output when in 
automatic mode and in PID.  
Typically configured with 100.0 %. 
sfst 
Softstart 
SoftStart Function – Time in seconds during which 
the controller limits the MV value progressively 
from 0 to 100 %. It is enabled at power up or when 
the control output is activated. If in doubt set zero 
(zero value disables the Soft start function). 
Sp.a1 
Sp.a2 
Sp.a3 
Sp.a4 
Alarm SP: Value that defines the point of activation 
for the programmed alarms with the functions “
Lo
” 
or “
ki
”. 
For the alarms configured with Differential type 
functions, this parameter defines deviation (band). 
Not used for the other alarm functions. 
CYCLE OF PROGRAMS 
t.bas 
Program time 
base 
Program time base - Defines the time base that will 
be used by all Ramp & Soak programs. 
Se( 
- Time basis in seconds 
min
 - Time basis in minutes 
Pr n 
Program 
number 
Selects the ramp and soak profile program to be 
edited/viewed. The sequence of parameters that 
follows refer to this selected program. Total of 20 
programs possible. There are 7 possible programs. 
Ptol 
Program 
Tolerance 
Maximum admitted deviation of PV w
ith respect to 
SP.If exceeded, the program execution is suspended 
(the internal timer freezes) until the deviation be 
returns back within the defined tolerance. 
The value 0 (zero) disables the function. 
Psp0
Psp7 
Program SP
Program SP’s, 0 to7: Group of 8 
values of SP that 
define the Ramp and Soak profile segments. 
Pt1
Pt7 
Program Time
Segments durations,  1 to7: 
Defines the time of 
duration, in second or minutes, 7 of the segments of 
the program being edited. 
Pe1
Pe7 
Program event
Alarms of Event,  1 to  7: 
Parameters that define 
which alarms are to be activated during the 
execution of a certain program segment. The alarms 
chosen must have its function configured as “
rS
”. 
Lp 
Link Program 
Link Program: number of the next profile program to 
be linked following the current program. Profiles can 
be linked together to produce larger programs of up 
to 49 segments
. 
  0 - do not link to any other program. 
  1 a 7 – number of the program to be linked to. 
PV Indication 
(Red Screen) 
SP Indication 
(Green Screen) 
PV Indication 
(Red Screen) 
MV Indication 
(Green Screen) 