Installation Manual

Installation
20 900-0111-01-00 Rev B
Install battery cable lug, nuts, and washers in the order illustrated. The battery cable lug should be the
first item installed on the stud. It should make solid contact with the mounting surface. Do not install
hardware in a different order than shown.
Figure 9 Required Order of Battery Cable Hardware
CAUTION: Fire Hazard
Never install extra washers or hardware between the mounting surface and the
battery cable lug. The decreased surface area can build up heat.
Mounting Surface
M8 x 1.25 Stud
Lock Washer
Battery
Cable Lug
13 mm Nut
Flat Washer
Insulator