OutBack Power SkyBox Quick Start Guide
Wiring
Commissioning
PV LED Legend
1a
2a
2
1c
3a 3b 4a 4b 5a 5b
6
11
900-0195-01-00 REV B
©2018 OutBack Power. All Rights Reserved.
5c 5d
1c
543
5c
5d
19. On the Home screen, check the SOLAR tile (as shown below) and
ensure it is operating normally. The SkyBox will connect to the PV source
if the voltage is above 250 Vdc. (See the SkyBox Overview Guide for more
information.)
20. If a generator is present: Turn off (open) the G
RID
circuit breaker
.
21. Start the generator. Do not turn on (close) the G
EN
circui
t breaker . Repeat steps 12 and 13 using ,
, and .
22. Turn on (close) the GEN circuit breaker . Repeat step
14. The L
OAD circuit breaker may remain on (closed).
23. Stop the generator.
24. Turn on (close) the G
RID circuit breaker .
Wait for the programmed connection delay to elapse.
Test any grid-interactive functions.
To de-energize or shut down the system:
There is no required shutdown order. It is common to de-energize circuits
in the reverse order from which they were energized.
65b
5a 5b
6
4a
4b
11
65a
CAUTION: Equipment Damage
Incorrect PV polarity will damage the equipment.
!
8. Verify 120 Vac on LOAD L1 by measuring with a DMM from to .
Verify L2 by measuring from to .
9. Verify 240 Vac across the L
OAD terminals by measuring from to .
10. Connect and test loads at the protected load panel.
11. If grid is present: Turn on the grid connection to the BOS at the source.
12. Verify 120 Vac on G
RID L1 by measuring with a DMM from to .
Verify L2 by measuring from to .
13. Verify 240 Vac across the G
RID terminals by measuring from to .
14. Turn on (close) the G
RID circuit breaker . The Wizard will appear
for the first time if no batteries are installed. (Perform steps 3 through 10
if this is the case.) The SkyBox transfer relay should click and the LOAD
tile should read PASS THROUGH.
15. Using a DMM, test the pass-through (transferred) L1 output voltage
at and . Test the L2 voltage at and .
16. If PV is present: Verify that the input is in the correct range of open-circuit
voltage. Confirm polarity by measuring with a DMM from to (referred to
as PV1 in the legend above). Confirm polarity from to (PV2, if present).
17. Check the green LED indicators and . If a single PV input is installed,
one indicator should light. If two strings are installed, both should light. Any
other behavior means the polarity may be reversed. Do NOT turn on the
switch. Review all PV connections.
18. Turn on (close) the PV switch . Check indicators and again. Both
indicators should light. Any other behavior means the polarity at the top of
the PV switch may be reversed.
7a8a
5
3
4
4
63a
63b
3a 3b
3
5c
5d
6
6
6
6
5c 5d
PRODUCING
KW
0 6
BEFORE CLOSING PV DISCONNECT
ENSURE LED INDICATION IS CORRECT:
TERMINALS ON PV BOARD CORRECT
ONLY PV1 TERMINALS
ONLY PV2 TERMINALS
PV1 + PV2 TERMINALS
NOTE: PV VOLTAGE > 100 VDC
REQUIRED TO LIGHT LEDS
3
NOTES
If any onscreen faults or other problems occur during commissioning, see the Troubleshooting section of
the SkyBox Overview Guide.
If installing multiple SkyBoxes in parallel, see the SkyBox Programming Guide for additional instructions.
See the CAUTION below for equipment requirements.
Setup Wizard
(entry screen)
Setup Wizard
(final screen)
Home Screen
!
7a 8a 8b7b
Caution
CAUTION: Reverse
polarity in negative
grounded system
Keep breaker in the OFF
position and check polarity
!
Pre-startup Procedures:
1. Double-check all wiring connections. Using a digital multimeter (DMM), test for continuity between
and . Ensure a neutral-ground bond is installed in the system.
2. Inspect the enclosure. Ensure no debris or tools were left inside.
3. Ensure all AC loads at the backup (or protected) load panel are disconnected.
4. Ensure all AC input feeds to the BOS are disconnected at each source.
5. Using a Phillips screwdriver, remove the clear plastic (dead front) panel (not depicted). The four
required screws are marked with in the image to the right.
6. Energize the system as below. Follow the procedures which are applicable
to the system. If any elements are not present (including batteries, PV, or
a generator), ignore those procedures.
6
5. Using a DMM, verify the inverted L1 output 120 Vac on the upper LOAD
terminals from
to . Verify L2 by measuring from to .
6. Verify 240 Vac across the LOAD terminals by measuring from to .
7. Turn on (close) the LOAD circuit breaker . Do not connect loads at the
protected load panel.
NOTES
Do not close the LOAD circuit breaker at this stage.
If the SkyBox is installed in a parallel-stacked system, read the Stacking
section of the SkyBox Programming Guide before proceeding
.
5
3. On the first power-up, a welcome message is shown. The right arrow
proceeds to the Setup Wizard. This steps through language, region, and
similar changes, then PV, battery, and AC settings. On the last screen,
the Save key proceeds to the Home screen. (The Home screen appears
after every subsequent power reset.)
4. From the Home screen, turn on the SkyBox with the O
N/OFF key .
To energize the Skybox:
1. If batteries are present: Verify input 48 Vdc using a DMM by measuring from
to .
If batteries are not used in this system, skip to step 11.
Confirm the correct battery voltage and polarity. If the red LED indicator
is lit, the polarity is reversed. Do NOT turn on the circuit breaker.
2. Once proper voltage and polarity are confirmed, turn on (close) the main
battery circuit breaker . Power-up may require up to 1 minute.
1c
1a 2a
2
CAUTION: Equipment Damage
All SkyBoxes require separate batteries, as each controls its own battery monitoring program. Using a
single, common battery bank will result in damage.
All SkyBoxes must use the same AC output bus. If they are connected to independent outputs, damage
will occur. Take the appropriate safety precautions when connecting the devices to the AC output.
All SkyBoxes must use the same AC input source. This may require the use of a bus bar. Take all
appropriate safety precautions when connecting to the AC input.
IMPORTANT
Enter BATTERY DETAILS under BATTERYtile programming.
Press the Reset
button. This will reset the battery state of charge (SoC)
to 100% and begin a new charge cycle.
WARNING: Shock Hazard
Before performing maintenance, all sources (battery, PV, and AC) must be
completely de-energized for at least five minutes.
CAUTION: Equipment Damage
Incorrect battery polarity will damage the equipment.
!