Horizontal Channels
Starting at the bottom of the REAR verticals:
1. Insert REAR horizontal channels into the
vertical channels. Center the horizontals
between the verticals. See Figures 11a & b.
2. Bolt horizontal channels to vertical channels.
Refer to below list for hardware order and
Figure 12:
NOTE:
The bottom two horizontals require full
thread longer bolts at the vertical channel.
Bottom horizontal:
Serrated Hex Bolt(M10x1.5 – 100mm
Full Threads),
Rack Frame,
External Tooth Washer,
Flat Washer,
Lock Washer,
Hex Nut
Second from bottom horizontal:
Serrated Hex Bolt (M10x1.5 – 75mm
Full Threads),
Rack Frame,
External Tooth Washer,
Flat Washer,
Lock Washer,
Hex Nut
All other horizontals:
Serrated Hex Bolt (M10x1.5 – 25mm)
3. Finger-tighten connections.
4. Install ALL REAR horizontals before
continuing.
INSTALL REAR HORIZONTAL CHANNELS
FIGURE 11A
INSTALL REAR HORIZONTAL CHANNELS
FIGURE 11B
REAR HORIZONTAL CHANNEL HARDWARE DETAIL
FIGURE 12
NOTE:
There may be two types of horizontal channels with
your shipment:
1) Rear – have four weld nuts
2) Front – have more than four weld nuts
The front horizontals are universal and, in most
configurations, are substituted for the rear horizontals.
Front horizontals are to be installed with the flange
positioned with the holes facing up.