M68333 Rev. A Tel-Link PMP - Sector Terminal Installation & Maintenance Manual 4-1
4.0 Site Preparation
Prior to beginning physical installation of the Tel-Link PMP equipment, the Site preparation work should be
complete. Site preparation includes but is not limited to the following:
Completed Site Survey Checklist (P-COM highly recommends the use and completion of the
Site Survey Checklist located in Appendix B)
System Configuration Document Specification
The criteria below should be evaluated prior to designating Remote to Sector terminal RF paths with the
use of Site Surveys and Link Budgets:
An unobstructed line-of-sight
Be within range (distance separation) with respect to the desired operational parameters (i.e.,
rain, region, availablity, modulation type, bit error rate performance, etc.)
Be within the antenna beamwidth
NOTE: P-COM highly recommends a blower or fan be used with an enclosed rack containing three
or more IDUs.
The IDU is designed to be installed in a 19-inch equipment rack or enclosed cabinet in a location that is:
Dry, clean and well ventilated
Easily accessible
Within 600 feet (with CAT-5 cable) of subsequent Customer Premise Equipment (CPE)
Within 1000 feet of the ODU when using LMR-400 or equivalent Coaxial cable
Compliant with all environmental specifications
4.1 ODU/Antenna Installation Preparation
Verify the location selected has the following characteristics:
Space on pole is adequate for mounting the antenna and ODU.
Verify the pole for the ODU/Antenna assembly is installed in the location identified on the Site
Survey Checklist.
Verify the pole has been securely installed and is grounded per local code.