User Manual

November 1999
11-2 M68333 Rev. A Tel-Link PMP - Sector Terminal Installation & Maintenance Manual
STEP 3. Connect the LSM to the LSM Interface Port of the Sector ATM Controller Card (refer to
Figure 11-1). Connection is via a straight through cable with Male/Female DB-9 con-
nections. The LSM should be running the P-COM WaveView software.
Figure 11-1 - LSM Interface Port of the Sector ATM Controller Card
STEP 4. Verify appropriate software is loaded in the Controller and in accordance with the Sys-
tem Configuration Document.
STEP 5. Verify the transmitter is disabled.
STEP 6. Sector Terminal Set the sac_Commissioning_Complete register to
No.
STEP 7. Load (Set and Get) appropriate registers in the IDU. Refer to the System Configuration
Document for appropriate frequencies, data rates, modulation schemes, etc. The icon
to the left of each of the configuration item's name should have a green plus symbol to
indicate successful loading of each configuration parameter.
RF IF DEMUX Green Blinking Operational
Off Fault
Red Solid On Fault
Off Operational
Table 11-1 - Board LED Indications
BOARD LED COLOR INDICATION DESCRIPTION
LSM Interface Port