PMP INSTALLATION PROCEDURE CHECKLIST
Technician(s)
Name:
Date:
INTRODUCTION
This Installation Procedure Checklist is provided to ensure correct installation procedures of P-COM PMP
equipment. The Checklist is to be completed for each site installed and the installer is to check-off each
step as completed. The installer will sign and date the Checklist and forward it to the P-COM Technical
Assistance Center (TAC) when the installation is completed.
Site Name:
Site Designation:
Sector Terminal Remote Terminal
FORMS:
Verify possession of completed Site Survey Form for the designated site.
Verify possession of System Configuration Document for the designated site.
Verify possession of Commissioning Test Form for the designated site.
INVENTORY:
The shipping list contains all equipment ordered by the customer for the total
number of Sector and Remote Terminals.
Verify possession of completed Site Survey Form for the designated site.
Verify possession of System Configuration Document for the designated site.
NOTE: Any visible damage should be reported immediately to the customer and to P-COM TAC
at: 1-(877) 674-3600
INTERFACILITY LINK (IFL) INSTALLATION SEQUENCE
IFL INSTALLATION
PREPARATION:
The IFL should be Times-Microwave LMR-400 coaxial cable, or equiv-
alent, unless otherwise stated in the P-COM Site Survey Form
Verify presence of an appropriate IFL between ODU and IDU locations.
Verify sufficient length (4 ft) of IFL exists at both ends to provide a service loop
prior to being terminated to the equipment.
Terminate each end of the IFL with Type-N male connectors.