OUTDOOR UNIT (ODU) INSTALLATION SEQUENCE
ODU/ANTENNA
INSTALLATION
PREPARATION:
Verify the pole used to mount the ODU/Antenna assembly is installed at the
location identified in the SIte Survey Form.
Verify the pole is securely mounted and connected to earth ground in accor-
dance with local code.
ODU/ANTENNA
INSTALLATION:
Install the ODU/Antenna assembly in accordance with the P-COM Installation
and Maintenance Manual.
Sector ODU/Antenna: Course align the antenna in the direction for operation
as specified in the P-COM System Configuration Document.
Remote ODU/Antenna: Align the antenna in the general direction of the desig-
nated Sector Terminal. Fine-tuning will be performed during the “Initial Power-
up and Test Sequence.”
ODU
INTERCONNECT:
Sector Terminal: Connect the IFL cable between the appropriate ODU and
Basic IDU Chassis.
Remote Terminal: Connect the IFL cable between the ODU RF Port (Type-N
Connector and Remote IDU.
INDOOR UNIT (IDU) INSTALLATION SEQUENCE
IDU INSTALLATION
PREPARATION:
Each Site should be identified, In the P-COM Site Survey Form, if the
IDU is to be rack mounted or placed on a tabletop.
Verify presence of IDU chassis and all cards intended to populate the IDU.
Verify presence of customer’s interface demarcation
Verify required rack/table is installed, secured to the floor, and ready to accept
the IDU.
Verify correct power source has bee provided within close proximity to the
location where the IDU is to be installed and is controlled through an appropri-
ate sized circuit breaker or fuse
Verify power to the IDU is in the Off position (AC) or disconnected (DC).