8'x8' 4' Ext. 8'x12'
Model Base Length No. of Packages
Glory Standard (8'x 8') 244.5 cm / 96.3" 2
Glory + 4' Ext. (8'x 12') 364 cm / 143.3" 3
Glory + 4' Ext. x2 (8'x 16') 483.5 cm / 190.4" 4
Glory + 4' Ext. x3 (8'x 20') 603 cm / 237.4" 5
ยป During Assembly
You may use Silicon lubricant spray in order to help you slide the panels into the profiles.
Do not spray the Polycarbonate panels.
Use a rubber mallet if necessary.
All panels with the stamped words THIS SIDE OUT must be facing out to create
full UV protection. Remove plastic sticker as panels are locked in place.
During assembly you will encounter the information icon, please refer to the
relevant assembly step for additional comments and assistance.
This icon indicates
that the installer should
be inside the product.
This icon indicates that
Ithe installer should be
outside the product.
Step 3: Refers only for the extension kit! The extension kit contains a base connector, either
part #8447 or #7601
Step 9: Please make sure the screw connection is made exactly as illustrated.
A - Connect the screw in the left hole.
B - Connect the screw in the right hole.
Step 10: Peel the film covering the panel. Make sure you install it with the UV protected side out.
Step 12: The screws inserted as shown in drawing b are to be used with the anchoring parts at
the end of the assembly.
Step 18: The screws inserted as shown in drawing c are to be used with the anchoring parts at
the end of the assembly.
Step 20: Side Louver Window: can be located only on one of the two central panels.
* If you assemble the greenhouse with an extension module, the window can be placed on all panels,
except for the last two end panels.
* Note: The selected placing will affect the next assembly steps.
Step 22: If there are screws in the rail as preparation for the anchoring stage, they can be used for the side
louvre window instead of part # 461.
It is not be possible to connect the anchoring part here.
Step 28: It is highly recommended to paste the sealing tape at the bottom edge of
panels 7903 + 7904 is order to prevent moisture seepage.
Step 35: Roof window can be located only on one of the two central roof panels.
* If you assemble the greenhouse with an extension module, the roof windows must be placed on panels
only as specified in the manual.
* Note: The selected placing will affect the next assembly steps.
Step 40: Please tighten screws from inside the greenhouse. In addition, please tighten the remaining
loose screws.
Step 45: As mentioned at the 'Before Assembly' section, prior to fitting the Automatic Vent Opener,
the power-tube has to be cooled by placing it in a refrigerator for approximately 30 minutes.
Step 54: Door can be installed as a left hand door or right hand door as per your decision. These
instructions show a right hand door assembly. Please determine door opening direction.This decision will
affect the next assembly steps.
Step 56: Please adjust the hinges height in accordance with the upper post and lower ramp of the door
aperture, as specified in Level C.
Step 60: Threading parts 7888 exactly as specified in Level B, is very important in order to create good
drainage.
Step 64: Anchor the shed on to a solid surface such as concrete or asphalt, use suitable screws and plugs.
(Screws and plugs are not supplied).
Important Recommendations
Firmly connect the greenhouse to a level surface immediately after completion of the assembly.
Anchoring this product to the ground is essential to its stability and rigidity.
It is required to complete this stage in order for your warranty to be valid.
Tighten all screws once assembly is completed.
Anchoring this product to the ground is essential to its stability and rigidity.
It is required to complete this stage in order for your warranty to be valid.
Screws 411 and nuts 412 are used throughout the assembly process.
Screws 411 are to be assembled from the outside and nuts 412 from the inside of the greenhouse.
If not specified otherwise, do not fasten screws and nuts (411 & 412) for more than 2-3 turns.
Do not tighten them until completion of the panels'assembly.
These 2 icons indicate if screw's tightening is required or not.
However, in some steps, temporary tightening of a few screws may be needed to prevent a
profile from sliding out.