Router User's Guide
Table Of Contents
- Contents
- About This Guide
- 1. About the FrameSaver SLV
- 2. User Interface and Basic Operation
- 3. Configuration Procedures
- 4. Configuration Options
- Using the Easy Install Feature
- Using RIP with FrameSaver SLV CSU/DSUs
- Entering System Information and Setting the System Clock
- Setting Up the Modem
- Setting Up Auto-Configuration
- Setting Up Dial Backup
- PVC Backup Over the Network Interface
- Setting Up Back-to-Back Operation
- Configuration Option Tables
- Configuring the Overall System
- Configuring Physical Interfaces
- Assigning Time Slots/Cross Connections
- Configuring Frame Relay for an Interface
- Manually Configuring DLCI Records
- Configuring PVC Connections
- Configuring the IP Path List
- Setting Up Management and Communication Options
- Configuring the Criteria for Automatic Backup
- 5. Configuring the FrameSaver SLV Router
- FrameSaver SLV Router Overview
- IP Routing
- Address Resolution Protocol
- Proxy ARP
- Interface Configuration
- Network Address Translation
- Network Address Port Translation
- Dynamic Host Configuration Protocol Server
- DHCP Relay Agent
- Router Security
- Provisioning the Router Interface
- Configuring the Router Using Terminal Emulation
- 6. Security and Logins
- 7. Operation and Maintenance
- 8. Troubleshooting
- 9. Setting Up OpenLane for FrameSaver Devices and Activating SLM Features
- 10. Setting Up NetScout Manager Plus for FrameSaver Devices
- 11. Setting Up Network Health for FrameSaver Devices
- A. Menu Hierarchy
- B. SNMP MIBs and Traps, and RMON Alarm Defaults
- C. Router CLI Commands, Codes, and Designations
- D. Router Command Line Summaries and Shortcuts
- E. Connectors, Cables, and Pin Assignments
- F. Technical Specifications
- G. Equipment List
- Index
8. Troubleshooting
8-20
September 2002 9128-A2-GB20-80
Starting and Stopping a Test
Use this procedure to start, monitor, or abort specific tests. To abort all active tests
on all interfaces, see
Aborting All Tests
on page 8-21.
Start or stop an individual test using the same procedure.
Procedure
To start and stop a loopback or a send-pattern test:
1. Follow this menu selection sequence:
Main Menu
→
Test
2. Select an interface and test (e.g., Network, Data Port, or ISDN PVC Tests) and
press Enter.
The selected test screen appears.
Start
appears in the Command column.
Inactive
appears in the Status column.
3. Select the Port number and press Enter.
4. Select the DLCI number and press Enter if a PVC test has been selected.
The cursor is positioned at Start in the Command column of the first available
test and is highlighted.
5. To start the test, highlight
Start
under Command for the test you want to run
and press Enter.
Stop
now appears and is highlighted, and the status of the
test changes to
Active
.
The length of time that the test has been running is shown in the Result
column.
6. To stop the test, press Enter to send the Stop command.
Start
reappears
and the status of the test changes back to
Inactive
.
When the status of a test is . . . The only command available is . . .
Inactive Start
Active Stop