User guide

16
Figure 3-13. Install the sliding rails
7. For 10K---Install the battery pack and battery protection plate,
then replace the front panel.
Figure 3-14. Installing the Cabinet
8. For 6K---Replace the battery tray, and connect the internal
battery connector, then replace the protection plate and the front
panel.
9. If installing additional UPSs, repeat from Step 1 to Step 8 for
each cabinet.
3.5.2 Installing the EBMs
Note: A little of arcing may occur when connecting an EBM to the
UPS. That is normal and not harmed. Plug the EBM cable into the
UPS battery connector quickly and firmly.