13 Decommissioning and disposal
Decommissioning
WARNING
EX pump only: Always observe the “Important supplements for dosing pumps in
EX areas” section of the “General Operating Instruction for ProMinent
®
Motor-Driven
Metering Pumps and Hydraulic Accessories”!
Metering pumps and their peripherals must be decommissioned by qualified or
authorised personnel.
For all dosing pumps for dosing flammable media, the following applies: start up and
draining only under specialist supervision.
When the pump is taken out of service, the pump housing and especially the liquid end
must be thoroughly cleansed of chemicals and dirt!
Always depressurise the discharge and suction line first before working on the pump!
When hazardous or unknown media are used, suitable protective equipment must be
worn when working on the liquid end.
Isolate the supply before working on the motor!
If an external fan, speed control or diaphragm rupture sensor are provided, isolate these
as well!
Check that no voltage is present!
Always secure the supply against unauthorised reconnection during work on the pump!
Final decommissioning Disconnect pump from mains
Rinse out the liquid end with a suitable rinse aid, rinse thoroughly if used with hazardous
materials
Drain out gear oil
TZHa: drain out hydraulic oil (2 drain plugs!)
Temporary decommissioning also:
Attach caps to valves
Place hose nozzle caps on hose nozzles
Ideally place the pump on a pallet
Cover the pump with a tarpaulin (allow ventilation from the back!).
Store pump in a dry, closed warehouse at
storage temperature -10 °C to 50 °C
humidity max. 95 % rel. humidity, non-condensing
Disposal
NOTICE
Observe all currently applicable local directives!
(particularly with regard to oils)
Decommissioning and disposal
BA_MA_TZ_006_10_06_GB.p65 05.02.2007, 13:41 Uhr44