Mounting VTrak in a Rack
Cautions
Do not install the VTrak unit into a rack without rails to support
the subsystem.
Do not lay one VTrak unit on top of another. Mount each
enclosure supported by its own set of rails.
Only a qualified technician who is familiar with the installation
procedure should mount and install the VTrak unit.
Be sure all switches are OFF before installing the VTrak unit
or exchanging components.
Mount the rails to the rack using the appropriate screws and
flange nuts, fully tightened, at each end of the rail.
Do not load the rails unless they are installed with screws as
instructed.
The rails that ship with the PROMISE VTrak unit are designed to
safely support that PROMISE VTrak unit when properly
installed. Additional loading on the rails is at the customer’s risk.
PROMISE Technology, Inc. cannot guarantee that the
mounting rails will support your PROMISE VTrak unit unless
you install them as instructed.
Verify that the maximum ambient temperature in the rack
system is less than the VTrak’s maximum environment
temperature. See page 10.
Verify that there is ample airflow around the VTrak unit.
Install all of your devices in the rack with their weight spread
as evenly as possible.
Determine the maximum amperage draw of all devices in the
rack and verify that it is less than the maximum amperage for
the rack’s power circuit. See page 10.
Verify that all devices in the rack are properly grounded,
especially any devices attached to power strips.
Note
To lighten the VTrak enclosure, remove the power supplies. If your
VTrak shipped with physical drives installed, remove all of the
drive carriers, also.