User guide

4
6. Installation
6.1 Location
Review the Safety section prior to installing the pump with AVA. It contains information required to
properly install and operate the AVA in an industrial environment.
Review the PULSAR
®
or PULSAR Shadow
®
Installation Operation Maintenance manual provided with
your metering pump. It details system related issues that are important to proper operation of the pump
and also the AVA. The AVA should be mounted in an area where the operator has access to the front of
the unit. Avoid locations where the AVA would be subjected to extreme cold or heat. Note the warning
statement on the next page. The installation of this device must comply with national, state and local
codes.
Allow 6 inches minimum clearance from the front of the AVA enclosure to allow for removal and
re-installation of the AVA as a unit.
Figure 2 Typical Installation.