HPSBOC 2512B v.1.1 HPSBOC 13,8V/2A/7Ah/OC Buffer switch mode power supply unit with technical outputs. EN Edition: 9 from 01.03.2018 Supercedes edition: 8 from 01.06.
www.pulsar.
www.pulsar.pl GREEN POWER plus HPSBOC2512B 1.2 Block diagram (fig.1). Fig.1. The block diagram of the PSU. 1.3 Description of the module’s components and connectors (tab.1, fig.2). Table 1. Elements of the PSU (see fig.2). Element no.
www.pulsar.pl HPSBOC2512B Fig. 2. The view of the PSU. Description of PSU components and connectors (tab.2, fig. 3). Element no. Description [Fig. 3] [1] PSU module [2] TAMPER, contact, sabotage protection (NC) Tab.2. The components of the PSU. Fig.3. The view of the PSU.
www.pulsar.pl HPSBOC2512B GREEN POWER plus 1.4 Specifications: - electrical parameters (tab.3) - mechanical parameters (tab.4) - operation safety (tab.5) - operating parameters (tab.6) Electrical parameters (tab.
www.pulsar.pl GREEN POWER plus HPSBOC2512B Mechanical parameters (tab.
www.pulsar.pl HPSBOC2512B GREEN POWER plus Before installation, prepare a PSU load balance. During normal operation, the total current drawn by the device may not exceed I = 2A*. Maximum battery charge current: 0,5A*. Total device current + * battery: 2,5A max . As the PSU is designed for a continuous operation and is not equipped with a power-switch, therefore an appropriate overload protection shall be guaranteed in the power supply circuit.
www.pulsar.pl HPSBOC2512B GREEN POWER plus 3.2 Technical outputs The PSU has indication outputs: EPS - absence of AC supply output: - OC type output that indicates AC power loss. Under normal status, with 230V AC supply, the output is connected to ground (L level – 0V). In case of power loss, the PSU will switch the output into high impedance state hi-Z after approx. 10s. - relay output indicating the absence of AC supply.
www.pulsar.pl HPSBOC2512B GREEN POWER plus 4. Operation and use. 4.1 Overload or short circuit of the PSU output (SCP on). In case of overload, the output voltage is automatically shut off, and so is the LED indicator. The restoration of the voltage takes place immediately after the failure (overload) is over. 4.2 Battery-assisted operation. In case of a main power outage, the device is immediately switched into a battery-assisted operation.
www.pulsar.pl GREEN POWER plus HPSBOC2512B WEEE MARK According to the EU WEE Directive – It is required not to dispose of electric or electronic waste as unsorted municipal waste and to collect such WEEE separately. The power supply unit is adapted for a sealed lead-acid battery (SLA). After the operation period it must not be disposed of but recycled according to the applicable law. Pulsar sp. j. Siedlec 150, 32-744 Łapczyca, Poland Tel. (+48) 14-610-19-40, Fax.