Installation manual
                                                PCX 256 PROGRAMMING MANUAL 
RINS868-6    Page: 53 
Test Bell? 
To Test the Bell press the key. All outputs 
programmed as either Bell or Strobe will be 
tested. “Testing Bell will be displayed” Press the 
 key to stop the test. ‘Test Bell’ will be 
displayed, press the  key. 
Do Battery Load Test? 
To perform a Battery Load Test, press the 
key. 
The Battery Load test will be started. 
Once the Battery test has completed, press the 
 key, ‘Do Battery Load Test’ will be displayed, 
press the key. 
Test PGMs? 
To test the PGMs press the key. 
Select the PGMs you would like to test (see page 
38 for the PGM types) and press the key. 
All outputs programmed as the type selected will 
be active. Press the key. The outputs will 
switch off. Repeat for other output types as 
required. Press the key. ‘Test PGM’s’ will be 
displayed. Press the key. 
Test PHC Communications? 
To test the PHC Communications press the 
key. This test is necessary to gain 
authorisation for connection to the network for 
SMS communication. 
‘Press Y if using PABX or N if not’ will be 
displayed. Press the key if you are using a 
PABX system or the key if not. 
Press the key once it has completed. ‘Test 
PHC Communications’ will be displayed, press 
the key. You will be returned to the Engineer 
Menu. 
If the test has failed please see page 65. 