Installation Procedure
Step 6 - Installing base stations and registration point
Once you’re confident that the bases are well sited, you should start your installation.
Use the cardboard templates provided in the base & the registration point boxes to mark the wall with
the correct fixing position.
Place the base station(s) at least 3m (9 ft) from finished floor level FFL (figure 2). The higher the better,
but NEVER above ceiling tiles.
A 24hr continuous power socket should be provided close to the position of the first base.
A single power supply will be enough for two bases plus the registration point over a maximum of
200 metres Cat5 cable length. If your installation requires more than two bases (plus the registration
point), a second 24hr continuous power supply should be provided in the line (see figure 3)
Note: power supplies can be located anywhere in the chain (i.e. any base can take the power feed).
page 6
Out socket In socket
RJ45 Out RJ45 OutRJ45 In RJ45 In
Primary
base station
Secondary
base station
Secondary
base station
RJ45 Out RJ45 OutRJ45 In RJ45 In
Secondary
base station
Secondary
base station
Power supply Power supply
max 100m max 100m max 100m max 100m
max 200m
gure 3 - Multi base station and registration point connections