4b.8: Electrical Connection
This heater is designed for single-phase 220/240V AC supply only. A circuit breaker must be
installed at the power supply and the electrical connection must comply with Local Supply
Authority Regulations and AS3000. It will require an approved, standard 240V 25A On / Off
switch in close proximity to the heater. Faulty wiring may void warranty if damage has been
sustained to the compressor from faulty or sub-standard wiring.
The specifications of the Australian Standard states that where an appliance is intended for
outdoor use (IPX5), it is not permitted to supply a power cord and plug. Therefore the owner will
need to employ a qualified electrical tradesperson to fit a 25A cable (suitably sheathed for exterior
use) with weatherproof electrical connector or plug to the unit.
A certified electrician must carry out all electrical work according to the local standards and
regulations. A separate circuit breaker is recommended for each unit in the case of multiple
installations. The power supply rating for the unit is 220-240V AC50Hz 25A.
Note: This water heater is fitted with a Digital Controller (thermostat) incorporating an
over-temperature energy cut out. Under no circumstances should the pool heater be operated
without this device being in the circuit. Only a qualified electrician or the manufacturer should
carry out replacement.
4b.9: High & Low Pressure Switch Cut Out Settings
Pressure Switch Setting Differential Settin
g
Low Pressure 50 kPa Cut Out 100 kPa
High Pressure 2,800 kPa Cut Out 400 kPa
IMPORTANT
This appliance is not intended for use by young children or the infirm without supervision – young
children should be supervised to ensure that they do not play with the appliance.
4c: Commissioning
Once all electrical and water connections have been correctly completed, commissioning can
begin.
4c.1: Temperature Rise Across Heat Exchanger
When carrying out the commissioning the expected temperature rise across the heat exchanger
would be between 4°C & 6°C on an ambient temperature of 20°C. Discharge pressure should be
between 1300 kPa & 1500 kPa when this temperature rise is achieved.
Document Number : QDC0046PD-6 Page 15 of 20