15. Commissioning
15.1 Initial lling of the system:
Remove the front panel of the case.
Lift the cap on the automatic air purger
valve 3 (Fig 15.1) one full turn and leave
open permanently.
2
3
Figure 15.1
Open the installer supplied automatic ll
valve between the cold water inlet and
Central Heating System.
Open each radiator air vent starting at the
lower point and close it only when clear
water, free of bubbles, ows out.
Purge the air from the pump by unscrew-
ing the pump plug 2 (Fig. 15.1); release the
pump by turning the rotor in the direction
indicated by the arrow on the information
plate.
Close the pump plug.
Continue lling the system. The actual
reading should ideally be 1.3 bar (19 psi)
and not less than 0.3 bar (4.3 psi).
Close all air release valves on the c.h.
system.
Inspect the boiler and the system for water
soundness and remedy any leaks discovered.
Cold ush the system to remove any
loose particles and any system debris be-
fore starting the boiler for the rst time.
Reassemble the front panel of the case.
Return ll valve to automatic position.
15.2 Lighting the boiler:
Note: If external controls are tted (e.g. room thermostat) ensure they “call for heat”.
THE BOILER AND ITS GAS CONNECTION MUST BE LEAK TESTED BEFORE THE
BOILER IS PLACED IN OPERATION
Turn on the electricity supply to the boiler, switching on the circuit breaker switch. The ap-
pliance operation light A will ash every 4 seconds.
Turn the function selector B as in Fig. 15.2. The appliance operation light A will ash every
2 seconds.
Figure 15.2
AB CDE