15. Commissioning
15.1 Initial lling of the system:
• Remove the front panel of the case.
• Lift the cap on the automatic air purger
valve 3 (Fig 15.1) one full turn and leave
open permanently.
2
3
Figure 15.1
• Open the installer supplied automatic ll
valve between the cold water inlet and
Central Heating System.
• Open each radiator air vent starting at the
lower point and close it only when clear
water, free of bubbles, ows out.
• Purge the air from the pump by unscrew-
ing the pump plug 2 (Fig. 15.1); release the
pump by turning the rotor in the direction
indicated by the arrow on the information
plate.
• Close the pump plug.
• Continue lling the system. The actual
reading should ideally be 1.3 bar (19 psi)
and not less than 0.3 bar (4.3 psi).
• Close all air release valves on the c.h.
system.
• Inspect the boiler and the system for water
soundness and remedy any leaks discovered.
• Cold ush the system to remove any
loose particles and any system debris be-
fore starting the boiler for the rst time.
• Reassemble the front panel of the case.
• Return ll valve to automatic position.
15.2 Lighting the boiler:
Note: If external controls are tted (e.g. room thermostat) ensure they “call for heat”.
THE BOILER AND ITS GAS CONNECTION MUST BE LEAK TESTED BEFORE THE
BOILER IS PLACED IN OPERATION
• Turn on the electricity supply to the boiler, switching on the circuit breaker switch. The ap-
pliance operation light A will ash every 4 seconds.
• Turn the function selector B as in Fig. 15.2. The appliance operation light A will ash every
2 seconds.
Figure 15.2
AB CDE
WARNINGS