12.0 INSTALLATION
12.1 POSITIONING
After unpacking the equipment and preparing the compressor room, put the machine into position, checking the
following items:
● Ensure that there is sufficient space around the machine to allow maintenance (see Fig. 12).
● Check that the compressor is standing on a perfectly flat floor.
ENSURE THAT THE OPERATOR CAN SEE THE WHOLE MACHINE FROM THE CONTROL PANEL AND
CHECK THE PRESENCE OF ANY UNAUTHORIZED PERSONS IN THE VICINITY OF THE MACHINE.
12.2 ELECTRICAL CONNECTION
• Check that the supply voltage is the same as the value indicated on the machine data plate.
CAUTION: the compressor Ref. 3 and the dryer Ref. 4 have two separate feeds, respectively three-phase or
single-phase and single-phase.
• Check the condition of the line leads and ensure that there is an efficient earth lead.
• Ensure that there is an automatic cut-out device upstream for the machine against overcurrents, with
a differential device (see Ref. 1 for compresseur Ref. 2 for dryer ) wiring diagram.
• Connect the machine power cables with the greatest care, according to the standards in force.
These cables must be as indicated on the machine wiring diagram.
ONLY PROFESSIONALLY SKILLED PERSONNEL MAY HAVE ACCESS TO THE ELECTRIC PANEL. SWITCH OFF
THE POWER BEFORE OPENING THE DOOR OF THE ELECTRIC PANEL.
COMPLIANCE WITH THE REGULATIONS IN FORCE CONCERNING ELECTRIC PLANTS IS FUNDAMENTAL FOR
OPERATOR SAFETY AND FOR THE PROTECTION OF THE MACHINE.
FIG. 12
3
1
1
2
3
4
1
THREE-PHASE OR
SINGLE-PHASE
SCREW-COMPRESSOR
SUPPLY LEAD.
SINGLE-PHASE DRYER
SUPPLY LEAD
PROTECT THE POWER
CABLE WITH A SUITABLE
CHANNEL
SPACE FOR MAINTENANCE
MINIMUM mt 1,5
MINIMUM mt. 2