Indoor Positioning Installation and Users Guide v1.0 7/15/2003
Installation Preparation
Prior to installation, the location of all LanPaks needs to be determined. A detailed map of the
areas to be covered will be required. These should be in .dwg or .dwx format and provided to
Radianse as early as possible. This map will be the basis for determining the positions of the
LanPaks throughout your facility. With the initial positions determined a final walkthrough to
determine exact locations will be required. At this time, any physical issues that will impact the
ability to install (ex. light fixtures, cabinets, etc) will be taken into account and final positioning
will be verified. A Radianse team member will work with you to complete this task.
In addition to the LanPak installation you should prepare the necessary information for the
LightPak installation. A detailed list of any resources that will be tracked should be obtained.
This could include a staff roster and/or equipment inventory.
LanPak Installation
Members of the Radianse team will install the LanPaks. Prior to installation, you should ensure
that all network ports have been installed, activated and tested. For installations using power
over UTP, this includes the installation and testing of the power injectors. For installations not
using power over UTP, the installation and location of electrical outlets should be verified.
A Radianse team member will be on-site for the installation of the LanPaks. As a result, detailed
installation and configuration instructions are not included. Should a LanPak require
replacement, any replacement equipment will be shipped to you pre-configured and ready to be
plugged into your network.
Should you need to remove an installed LanPak, slide the LanPak upward and then away from
the wall to remove it from the bracket. Unplug the power cord (if one exists) from the back of
the LanPak (Note: most LanPaks will not have a separate power cord) and then unplug the
network cable from the LanPak.
With the old LanPak removed, you can now install the new LanPak. Plug the network cable and
the power cable (if one exists) back into the LanPak. Place the new LanPak on the bracket,
lining up the mounting holes, and slide the LanPak downward to lock it into place. Plug the
network cable back into the data port. Once installed, any extra cable can be tucked behind the
LanPak.
LightPak
LightPaks come preconfigured and ready for use. There is no hardware setup required.