Installation Guide
Table Of Contents
- Title
- Contents
- Introduction
- System Description
- Pre-Installation
- Receipt of Equipment
- Site Planning
- Main Rack and Supporting Hardware
- Remote ACUs
- RFUs
- RadioBlades
- RAPs
- URU
- Interconnecting Cabling
- Main Rack Configuration
- RF Planning
- Site Survey
- Alarm Configuration
- Tools Required
- Installation
- Equipment Commissioning
- iDEN Interface
- Power Plant
- RadioFrame System
- Coverage Validation
- Site Acceptance Guidelines
- RadioFrame System Functionality Test
- RadioFrame System iDEN Functionality Test
- Interconnect & Dispatch Setup & Voice Quality
- Packet Data Service Connection and Latency
- Short Message Service
- Handover and Cell Reselection
- Interconnect Connection Stability and SQE Performance
- Dispatch Connection Stability
- Idle SQE Testing and Validation
- System Self-Recovery Test
- Packet Data Stability and Throughput
- Validation of ‘Unable to Key BR’ Alarm
- Rectifier & AC Power Alarms
- iSC-3 Functionality Test
- RadioFrame System iDEN Functionality Test
- Connecting the RFS to the Customer LAN
- Operations and Maintenance
- Appendixes
RadioFrame System
Pre-Installation
RFN_3.1 Beta 49
3.8.5 Grounding
• No additional grounding is required
• A ground point for chassis ground is provided: #4 screw with internal sems
washer
3.8.6 Environment
• Operating Ambient Temperature: 0
o
C to +40
o
C (+32
o
F to +104
o
F)
• Altitude: -200 to +8000 feet above mean sea level; above 8000', reduce
maximum operating ambient temperature by 2
o
C per 1000' to a maximum of
13000'
• Storage Temperature: -40
o
C to +70
o
C (-40
o
F to +158
o
F)
• Relative Humidity: 10-90% non condensing
• Shock: 40 g’s
• Vibration: Level 3 earthquake
• Keep product free from dust, wind, salt, liquids
3.8.7 Heat Load
• Not applicable
3.9 Interconnecting Cabling
Site planning requires true single point grounding. The Telco entrance and Telco
termination board should be located as close to the transmission line entry and
AC service entrance as possible. This enables the individual
ground leads to
bond to a single point, with the least amount of distance between the ground
leads.
3.9.1 T1
T1 lines are used to connect the RadioFrame System with the Mobile Switching
Center (MSC). Each RFN customer iDEN/802.11b RFS site is typically fed with a
single T1 line, and subsequently protected with a surge suppressor. The
suppressor is located between the "smart jack" (maintained by the local
telephone company) and the Channel Service Unit (CSU). The suppressor
should be grounded downward directly to the master ground bus (MGB) using a
#6 AWG green wire.
The Telco board and the MGB should be mounted adjacent to each other on the
same wall (the coax ground and power ground should also be at this same