Installation Guide
Table Of Contents
- Title
- Contents
- Introduction
- System Description
- Pre-Installation
- Receipt of Equipment
- Site Planning
- Main Rack and Supporting Hardware
- Remote ACUs
- RFUs
- RadioBlades
- RAPs
- URU
- Interconnecting Cabling
- Main Rack Configuration
- RF Planning
- Site Survey
- Alarm Configuration
- Tools Required
- Installation
- Equipment Commissioning
- iDEN Interface
- Power Plant
- RadioFrame System
- Coverage Validation
- Site Acceptance Guidelines
- RadioFrame System Functionality Test
- RadioFrame System iDEN Functionality Test
- Interconnect & Dispatch Setup & Voice Quality
- Packet Data Service Connection and Latency
- Short Message Service
- Handover and Cell Reselection
- Interconnect Connection Stability and SQE Performance
- Dispatch Connection Stability
- Idle SQE Testing and Validation
- System Self-Recovery Test
- Packet Data Stability and Throughput
- Validation of ‘Unable to Key BR’ Alarm
- Rectifier & AC Power Alarms
- iSC-3 Functionality Test
- RadioFrame System iDEN Functionality Test
- Connecting the RFS to the Customer LAN
- Operations and Maintenance
- Appendixes
Method of Procedure
Equipment Commissioning
82 RFN_3.1 Beta
5 Equipment Commissioning
The procedures in this chapter describe how to conduct final checkout and
system test procedures for each portion of the iDEN/802.11 RadioFrame System,
including the iDEN Interface, the Power Plant, and the RFS. Following the
successful completion of procedures described in this chapter, the RFS can be
connected to the customer LAN as described in Chapter 6 “Connecting the RFS
to the Customer LAN”.
The procedures in this chapter are to be used in conjunction with troubleshooting
and repair information provided in Chapter 7 Operations and Maintenance and
the RFN document, Field Guide to the RadioFrame System. Together, these
troubleshooting solutions and commissioning procedures provide the necessary
information to isolate failures to a Field Replaceable Unit (FRU). This minimizes
system downtime by quickly returning the site to normal operation.
This chapter’s procedures check system functions and help isolate failures down
to the FRU level. If a failure cannot be isolated after performing these tests, refer
to Chapter 7 “Operations and Maintenance” for technical assistance information.
5.1 iDEN Interface
Perform the following procedures described in the Gen 3 Site Controller System
Manual, Motorola, 68P80801E30-O:
Chapter Procedure Title
5 Final Checkout Final Checkout Setup
Powering the Site Controller Rack
Circuit Breakers
6 System Testing Site Controller Startup Sequence
T1 Connection Test
EAS Alarm Checkout
GPS Status
5.2 Power Plant
Perform the following procedures described in the PEC 127NHL Manual,
PECO II, 438127NHL-IBWS-PD:
Chapter Procedure Title
4 Initial Turn On and Acceptance Test Procedures Complete Operational Checkout
Alarm Tests
BTC Probe Compensation Test