2.5 Installation Sequence
The WinLink1000 system installation is achieved by following the steps
listed below:
1. Installing ODUs at both sites of the link.
2. Assembling the ODU cable and connecting ODU to IDU at both
sites.
3. Connecting the power.
4. Installing the management program on the network management
station.
5. Aligning the ODUs.
6. Use the Link Budget Calculator Application
7. Running the Installation wizard from the management program.
8. Connecting user equipment to the local and remote IDUs.
Figure
2-1
illustrates a typical installation of WinLink1000 with an
external antenna.