5
Regardless if you’re creating a new configuration or simply loading a pre-defined configuration, you will
need to install, start, and use the Mongoose Tracker software.
Note: e order of this task in the installation process is somewhat flexible. If you prefer, you can
install and connect the Remote Audio Devices (RADs) prior to loading the configuration file. ere are
advantages, however, in loading the configuration first. Whether or not the configuration is loaded, if the
Mongoose is powered on and connected prior to installing the RADs, you can determine immediately
upon installing a RAD (by observing its status indicators) if it is functioning properly. If the configuration
is also in place, however, you can immediately determine if the RAD model you just installed matches the
model specified in the Mongoose configuration (if there’s a mismatch, the RAD’s status indicators flash
red). Also, if you have wireless access to the Mongoose, loading the configuration file early in the process
makes it possible to then view the configuration from a laptop as you’re installing the RADs. If you do not
have a configuration file and you plan to simply test that the installed equipment can successfully send and
receive audio, disregard this recommendation. You will create a simple test configuration after you have
installed all of the equipment. For details see "Task 2: Loading a Configuration File" on page 20.
Task 3: Pull and terminate the CAT 5 cabling for the RADs.
Each RAD connects to its host Mongoose via a CAT 5 cable. We recommend pulling this cable prior to
installing the RADs because this makes it much easier to troubleshoot the installation of the RADs. Note
that each RAD requires a home run. As noted in the previous task, if the CAT 5 cables are installed and
terminated, and the Mongoose is powered on and connected, you can verify if the RADs are working
properly as soon as you connect them. For details on this task, see "Task 3: Pulling the CAT 5 Cable" on
page 22.
Task 4: Install and connect the individual RADs.
is task involves the connection of the RADs to the CAT 5 cable, followed by the physical installation of
the RADs into the switchboxes in the wall. A key part of this task is to doublecheck that you are installing
the correct RAD models in each location. e wiring diagram should specify which RAD models go
in which locations. Also, if you load the Mongoose configuration prior to installing the RADs, you can
view the RAD’s status indicators to determine if you have installed the correct model. If the models do
not match, the RAD’s bottom four LED indicators flash red. In addition to verifying that you’ve installed
the correct model, this task involves the verification that the RAD hardware is communicating properly
with the Mongoose. Again, the RADs LED indicators provide this information. For details, see "Task 4:
Installing the RADs" on page 23.
Task 5: Verify connections, perform audio test, troubleshoot, and save the final configuration.
After installing the Mongoose, the RADs, and the configuration file, you need to verify that everything is
working properly. See "Task 5: Verifying and Finalizing the Installation" on page 27.
Important Note for Installers who do not have a Configuration File: If you do not have a pre-defined
configuration file but you want to verify that the equipment works, you need to create a simple verification
configuration. See "Creating a Verification Configuration" on page 31 for details.