Step 7. DRYWALL Wall Preparation
When installing into drywall, a piece of 81” x 5 1/2” x 7/8”
solid wood blocking is required to be mounted to the wall
before proceeding with the rail installation.
Position the solid wood blocking by measuring up from
the door height (H) + 1 3/4” to the centre of the track. Also
ensure a gap of 3/8” - 1/2” at the bottom. Lastly, ensure the
solid wood blocking is level and leave a minimum of 2” from
the end of the blocking to the side of the opening (as shown).
If installing with an opening for 80” standard door size,
remove the top trim and cut the side trim horizontally along
the height of the opening.
Step 8. DRYWALL Wall Preparation
Position the rail on top of the wood blocking ensuring
levelness, mark the holes using a pencil and pre-drill
5/16" holes into the wood blocking.
1 3/8" (30mm)
5/16" (8mm)
Step 9. DRYWALL Rail Installation
When installing into the solid wood block and wall, insert
using the provided wall screws. Align each spacer to the
rail holes, inserting spacers and screws (with washers),
securing with a wrench.
Ensure to insert both stoppers either side of the rail inside
the rst hole.
Door Height + 1 3/4
"
81 3/4" (L) X 5 1/2" (H) x 7/8" (D)
78 3/4" (2000mm)
Minimum
2"
(51mm)
3/8" (9.5 mm) –
1/2" (12.7 mm)
Gap under
the door