11.9 Cleaning/replacing the ignition/ionisation electrode
Remove the two retaining screws on the electrode assembly, remove assembly and
examine for wear and dirt, clean and re-gap electrode (3mm) if in good condition.
Replace electrode assembly if necessary - then discard screws and gasket and
fit replacement assembly c/w new gasket and screws making sure that the earth
connection is in good condition and in contact with the base plate
11.10 Cleaning to inspection glass
Remove the two retaining screws on the inspection glass holder, clean and replace.
Re-assemble boiler in reverse order, check front plate gasket and insulation piece,
replace if required also check gasket on fan and on gas valve, replace if necessary.
Ensure that all cables are routed correctly using existing clips and ties were possible to
ensure that they do not touch any hot parts of the boiler
Commission boiler in accordance with Par. 9.1- complete site report and/or boiler log
book if present