Installation Guide
SM
SOLAR
MOUNT
INSTALLATION GUIDE
PAGE
POSITION T-BOLT ALIGNMENT MARKS
& CUT RAIL: Verify that the position
indicator(s) & T-bolt shaft(s) are
angled in the correct position. Trim
off any excess rail, being careful not
to cut into the roof. Allow ½” between
the Endclamp and the end of the rail.
FINISH MODULE INSTALLATION: Proceed with module installation. Engage each
module with the previously positioned clamp assembly:
• Install second module
• Install remaining Midclamps & modules & position alignment marks
• Install Endclamps & position alignment marks
• Cut rail to desired length
INSTALL ENDCLAMPS: Apply Anti-Seize
and install nal Endclamps in same
manner as rst Endclamps. Slide
clamps against module.
TORQUE VALUE (See Note on PG. Q)
1/4” nuts to 10 ft-lbs. w/Anti Seize
REMAINING MODULES & TRIM
V
1/2"
MIN.
INSTALL REMAINING MID-CLAMPS:
Proceed with module installation.
Engage each module with previously
positioned Midclamp assemblies.
NOTE: Apply Anti-Seize to each Mid
Clamp prior to installation.
POSITION T-BOLT ALIGNMENT MARKS:
Verify that the position indicator(s)
& T-bolt shaft(s) are angled in the
correct position.
TORQUE VALUE (See Note on PG. Q)
1/4” nuts to 10 ft-lbs. w/Anti Seize
FINISH TRIM INSTALLATION, INSTALL
ENDCLAMP & CUT EXCESS RAIL:
Install nal endclamp & Cut away
excess Trim at end of array or where
required for proper cantilevers. See
D&E Guide or U-Builder for allowable
cantilevers.
TORQUE VALUE (See Note on PG. Q)
1/4” nuts to 10 ft-lbs w/ Anti Seize
TRIM INSTALLATION INSTRUCTIONS