ProjectPlan
Task Duration Start Finish Predecessors
1Teamformation 0days 10/23/200710/23/2007
2Researchpreviousteam'sproject 17days 10/23/200711/14/2007 1
3Firstsponsormeeting 1day 10/30/200710/30/2007 1
4Proposedprojectimprovementstosponsor 1day 11/15/200711/15/2007 2
5Inventoryofmaterials 1day 11/15/200711/15/2007 2,3
6AnalysisandtestingofDigiDev.Board 10days 11/16/200711/29/2007 5
7Reviewoflastyear'sdesign(withTA) 1day 11/30/200711/30/2007 6,4
8Redefineprojectspecs 10days 12/3/200712/14/2007 7
9HomeControlServer‐LightingControl 58days 12/17/2007 3/5/2008
10 InstallLinuxUbuntuOS 5days 12/17/200712/21/2007 7,8
11 Installlastyear'scontrolsoftware 1day 1/7/2008 1/7/2008 10,18
12 ImplementInsteondemo 5days 1/8/2008 1/14/2008 11
13 Designlightingcontrolscenarioforspecifichouse 5days 1/15/2008 1/21/2008 12
14 Installlightingcontrolinhome 10days 1/22/2008 2/4/2008 13
15 Testlightingcontrol 20days 2/5/2008 3/3/2008 14
16 Documentresults/operation 2days 3/4/2008 3/5/2008 15
17NetworkManagedThermostat 89days 11/30/2007 4/2/2008
18 Individualresearchofcommercialthermostats 26days 11/30/2007 1/4/2008 6
19 Commercialthermostatselected 0days 1/4/2008 1/4/2008 18
20 Definespecifications/functionality 5days 1/7/2008 1/11/2008 19
21 Customthermostatdesign 10days 1/7/2008 1/18/2008 19
22 Orderandshipparts 10days 1/21/2008 2/1/2008
21,20
23 Receiveparts 0days 2/1/2008 2/1/2008 22
24 Buildandtestprototypethermostatinlab 15days 2/4/2008 2/22/2008 23
25 Testingcommercialthermostatcommunications 15days 2/4/2008 2/22/2008 23
26 Setupandtestservercontrolofthermostats 10days 2/25/2008 3/7/2008 25,24
27 Testprototypethermostatinhome 10days 3/10/2008 3/21/2008 26
28 Implementfinalthermostat 5days 3/24/2008 3/28/2008 27
29 Documentresults/operation 3days 3/31/2008 4/2/2008 28
30FinalDocumentation 5days 4/3/2008 4/9/2008 29,16
31PosterDesign 2days 4/3/2008 4/4/2008 29
32DesignDay 0days 4/22/2008 4/22/2008 30,31,15,28
ForcompleteGanttchart,seeAppendixB.