ID Task Name Duration Start Finish Predecessors
1 Team formation 0 days Tue 10/23/07 Tue 10/23/07
2 Research previous team's project 17 days Tue 10/23/07 Wed 11/14/07 1
3
First sponsor meeting 1 day Tue 10/30/07 Tue 10/30/07 1
4
Proposed project improvements to sponsor 1 day Thu 11/15/07 Thu 11/15/07 2
5
Inventory of materials 1 day Thu 11/15/07 Thu 11/15/07 2,3
6
Analysis and testing of Digi Dev. Board 10 days Fri 11/16/07 Thu 11/29/07 5
7
Review of last year's design (with TA) 1 day Fri 11/30/07 Fri 11/30/07 6,4
8
Redefine project specs 10 days Mon 12/3/07 Fri 12/14/07 7
9
Home Control Server - Lighting Control 58 days Mon 12/17/07 Wed 3/5/08
10 Install Linux Ubuntu OS 5 days Mon 12/17/07 Fri 12/21/07 7,8
11
Install last year's control software 1 day Mon 1/7/08 Mon 1/7/08 10,18
12
Implement Insteon demo 5 days Tue 1/8/08 Mon 1/14/08 11
13
Design lighting control scenario for specific house 5 days Tue 1/15/08 Mon 1/21/08 12
14
Install lighting control in home 10 days Tue 1/22/08 Mon 2/4/08 13
15
Test lighting control 20 days Tue 2/5/08 Mon 3/3/08 14
16
Document results/operation 2 days Tue 3/4/08 Wed 3/5/08 15
17
Network-Managed Thermostat 89 days Fri 11/30/07 Wed 4/2/08
18 Individual research of commercial thermostats 26 days Fri 11/30/07 Fri 1/4/08 6
19
Commercial thermostat selected 0 days Fri 1/4/08 Fri 1/4/08 18
20
Define specifications/functionality 5 days Mon 1/7/08 Fri 1/11/08 19
21
Custom thermostat design 10 days Mon 1/7/08 Fri 1/18/08 19
22
Order and ship parts 10 days Mon 1/21/08 Fri 2/1/08 21,20
23
Receive parts 0 days Fri 2/1/08 Fri 2/1/08 22
24
Build and test prototype thermostat in lab 15 days Mon 2/4/08 Fri 2/22/08 23
25
Testing commercial thermostat communications 15 days Mon 2/4/08 Fri 2/22/08 23
26
Setup and test server control of thermostats 10 days Mon 2/25/08 Fri 3/7/08 25,24
27
Test prototype thermostat in home 10 days Mon 3/10/08 Fri 3/21/08 26
28
Implement final thermostat 5 days Mon 3/24/08 Fri 3/28/08 27
29
Document results/operation 3 days Mon 3/31/08 Wed 4/2/08 28
30
Final Documentation 5 days Thu 4/3/08 Wed 4/9/08 29,16
31
Poster Design 2 days Thu 4/3/08 Fri 4/4/08 29
32
Design Day 0 days Tue 4/22/08 Tue 4/22/08 30,31,15,28