Rinnai I-Series Condensing Boiler Solo Manual
You Will Need:
Philips head screwdriver
1. Remove the boiler’s front panel by removing the four screws that secure the panel.
3. Fill the boiler to a minimum of 20 PSI (138 kPa) water
pressure and a maximum of 30 PSI (207 kPa).
4. The deaeraon process takes approximately 15 minutes
for compleon.
Aer 15 minutes, the display will show “End” (see right
image). The commissioning process is complete.
5. On the PC Board, press the black buon again to resume
normal operaon mode.
6. Operate the central heang to ensure the boiler operates
properly.
7. Close the air vent located inside the boiler. Aer
approximately one week, all air in the system should be
eliminated via the air separator in the piping system.
DIP Switches
Note: Alternately, on inial installaon, you may press and hold
the Indirect Tank buon, then simultaneously press the CH buon
on the control panel instead of removing the boiler’s front panel.
2. On the PC Board, press and hold the top, le black buon shown below. The Maintenance
Required icon (see right image) on the controller display will appear.
PC Board