Installation Manual
Rinnai I-Series Condensing Boiler Solo Manual 69
Failure to properly commission the boiler as
described in this secon may result in
unreliable and unsafe burner operaon and
reduced component life.
Boiler commissioning is a procedure used
aer boiler installaon to ensure the system
and boiler were installed correctly and ready
for operaon.
THIS SECTION IS INTENDED
FOR THE INSTALLER
This boiler must be commissioned by a
licensed professional. Installer qualicaons:
A trained and qualied professional must
install the appliance, inspect it, and leak test
the boiler before use. The warranty will be
voided due to any improper installaon. The
trained and qualied professional should
have skills such as: Gas sizing; Connecng
gas lines, water lines, valves, and electricity;
Knowledge of applicable naonal, state, and
local codes; Installing venng through a wall
or roof; and training in installaon of
condensing boilers. Training for Rinnai
Condensing Boilers is accessible online at
www.trainingevents.rinnai.us.
1. Ensure all boiler components are installed
correctly.
2. Open the air vent inside the boiler.
3. Power on the boiler.
4. Open the ll valve on the lling circuit.
5. Check the pressure on the controller and/or
pressure gauge. Fill the boiler to a minimum of
20 PSI (138 kPa) water pressure and a maximum
of 30 PSI (207 kPa).
6. An E430 diagnosc code will be present unl the
boiler senses at least 13 PSI (90 kPa).
7. Check the heang system for leaks.
8. Begin the deaeraon process shown in the next
secon (“10.3 Deaeraon Process”).
• Work on the boiler must be carried out
by a licensed professional, using
correctly calibrated instruments with
current test cercaon. The
commissioning instrucons are intended
for licensed professionals who have the
necessary knowledge and are approved
for working on heang and gas systems.
• The fan will operate when power is
inially provided to perform a safety
check on the boiler.
• The boiler and its individual shut o
valve must be disconnected from the gas
supply piping system during any
pressure tesng of that system at test
pressures in excess of 1/2 PSI (3.5 kPa).
• Before the boiler is red for the rst
me:
− Ensure the boiler and system are
fully de-aerated
− Purge the gas line between the gas
meter and boiler
− Prime the pump (as described in this
secon)
IMPORTANT
IMPORTANT
Topics in this secon
• Safety Precauons
• Filling Process
• Deaeraon Process
10
WARNING
Do not ll the boiler unless permanent
power is available. Freeze protecon is not
available if the boiler is not lled, air
purged, and supplied with power and gas.