Installation manual
Rinnai New Zealand Limited Neo Installation Manual: 11906-B
02-11
16
Mock chimney installaons
1. Construct frame and install zero clearance box
Refer 'Enclosure dimensions' and construct frame. Assemble and install the RIB2310 zero
clearance box. Installation needs to be on a level base. If this is not done the appliance may
twist and become damaged—this will void any product warranty.
The zero clearance box is installed ush with the cladding surface.
For installations into a mock chimney a Rinnai zero clearance box and zero clearance ue kit is
required to isolate the appliance from combustible materials. Failure to meet this installation
criteria will void any product warranty.
800 mm
650 mm min.
370 mm min.
7
2. Install the ue and complete electrical connecon
The weight of the ue system should not be supported by the appliance—it should be self-
supporting. Supporting the ue is usually completed during the framing stage with ue
supports or straps within the cavity. Flue supports have been included with the ue kit to assist
with this. These are to be riveted to the ue.
Please note, a twin-skin ue requires a 25 mm clearance (from the outer ue) from
combustibles.
Combusble Material
(must be greater than 50 mm from inner flue)
Flue
Inner flue 100 mm
Outer flue 150 mm