13 If A XX appears on the display, wait for 17 minutes;
14 Check the water pressure and if necessary top it up to 16 to 18 PSI (1.1 and 1.3 bar)
15 Close the lling loop;
16 Press the ‘STEP’-button;
17 Be sure that the lling loop is closed.
18
After the automatic de-aeration program (A XX) is nished the boiler will return to
the Good state or Technical read out.
Check the water pressure regularly and top off the installation when necessary.
The typical working pressure of the installation should be between 16 and 18 PSI (1.1
and 1.3 bar) when the system is cold.
It can take a while before all air has disappeared from a lled installation.
Especially in the rst week noises may be heard which indicate the presence
of air. The automatic air vent in the boiler will remove the air, which means the
water pressure can reduce during this period and therefore topping off with
water will have to be done.
During normal use the following messages can occur with the necessary follow up:
NOTICE
i
Water pressure is too low (<12 PSI / 0.8
bar), flashing FILL will alternate with
indication of water pressure, boiler power
of 50% is possible. The installation needs
to be topped off.
Water pressure is too high (>42 PSI
/ 3 bar), if HIGH indication remains
continuously visible, the boiler is taken
out of operation. The installation pressure
needs to be decreased by draining water.
Water pressure is too low (<10 PSI / 0.7
bar), FILL indication remains continuously
visible, the boiler is taken out of operation.
The installation needs to be topped off.
10.3 Hot water supply (only Q175C)
Apply the water pipe pressure to the tank (open main valve and/or stop valve of the
safety group).
Vent the tank and the hot water installation by opening a hot water shut off valve.
Leave the tap open for as long as required until all air has disappeared from the tank