Installation manual

Rinnai 13 RF1800 OIM
Flue Components
A. RFPIPE150
900mm twin skin ue pipe -
ø 150mm inner / ø 200mm outer
(approx 855mm when installed)
B. RF1800YPIECE
1. Y piece collector box (1x) -
2x ø 150mm inner / ø 200mm outer to
1x ø 200mm inner / ø 250mm outer.
2. 45° twin skin bends (2x) -
ø 150mm inner / ø 200mm outer.
3. 150mm ue pipe (2x) -
ø 150mm.
4. 200mm ue pipe over-wraps (2x) -
ø 200mm.
(height approx 615mm when installed)
C. RFPIPE200
900mm twin skin ue pipe -
ø 250mm inner / ø 300mm outer
(approx 855mm when installed)
D. RFCOWL200
Connection ø 200mm, Outer ø 350mm
E. RFBEND150
2x 45° twin skin bends -
ø 150mm inner / ø 200mm outer
(height approx 322mm when installed)
F. RFBEND200
2x 45° twin skin bends -
ø 200mm inner / ø 250mm outer
(height approx 357mm when installed)
G. RFCOWL150
Connection ø 150mm, Outer ø 300mm
Y Piece Collector Box Assembly
1. Fit the RFPIPE150 ue pipes (A) onto the engine using rivets and sealant as required.
2. Fit the ø 150mm inner 45° bends (B2) but do not x in place yet.
3. Fit the ø 200mm outer 45° bends (B2) and leave loose.
4. Fit the two 150mm ø 460mm lengths of ue pipe (B3) to the ø 150mm inner connections of the Y piece
collector box (B1), then t and square up with the assembly from above. Then x all but the ø 200mm outer
45° bends (B2) in place.
5. Fit the two 200mm over-wraps (B4) over the ø 200mm outer 45° bends (B2) and the ø 200mm outer
connections of the Y piece collector box (B1) and x all in place.
6. Complete the ue to the termination point using RFPIPE200 (C) and RFCOWL200 (D) as required.
IMPORTANT
The minimum total ue height is 2.4 metres, providing the ue is direct without offsets.
Offsets can be used on ues over 3.6 metres in height.
B4
B3
C
B4
B3
B2
A
B2
B1
D
G
E
A
F
A
C