Installation Manual
19
HE+ Series Infrared Gas Heater Installation and Operation Manual
FIGURE 8: INSTALL BURNER TO COMBUSTION TUBE
1. Suspend combustion tube in first two hangers:
• Hole for connection rivet at side of combustion tube
• Welded seam of combustion tube facing downward
(in the bottom hemisphere)
2. Slide tube coupler on to combustion tube
(past the rivet hole in tube)
3. Insert the burner tube (swage) into the combustion tube
4. Align rivet holes in combustion and burner
tubes. A screwdriver or similar tool can assist
alignment
5. Insert rivet into the aligned holes
6. Slide tube coupler over rivet head and locate
coupler half on burner tube and half on com-
bustion tube
7. IMPORTANT: Torque coupler nuts to 40 lb-ft
8. Adjust (rotate) burner to ensure hanging plumb
9) Subsequent lengths of tube can then be installed, by inserting the swaged portion inside the
next tube and locking the joint using the Torctite coupler. SEE FIGURE 9.
NOTE: For the 3rd and following tubes in the system: DO NOT install the welded seam facing
downward along the length of the system after the first two tubes. Welded seams should ran-
domly face toward one side or the other (3 or 9 o’clock), 90° up from bottom (6 o’clock).
10) If there is a 90° elbow in the system refer to Section 7 and Figures 3 & 4
FIGURE 7: STRAIGHT TUBE TYPICAL HANGER & SUPPORT SPACINGS
9 - HEATER SUSPENSION
CHAIN / CABLE
OPTIONAL:
10 - FLUE VENT TERMINAL
11 - 4” AIR DUCT WALL CAP
4 - WIRE HANGERS
5 - STEEL HEAT EXCHANGE TUBES
6 - TORCTITE TUBE COUPLER
7 - ALUMINIZED STEEL REFLECTOR
8 - REFLECTOR END CAP
1 - BURNER ASSEMBLY
2 - SIGHT GLASS WIRE HANGER
3 - COMBUSTION TUBE:
• UP TO 155,000: ALUMINIZED STEEL
• > 155,000: STAINLESS STEEL
SUSPEND ALL TUBES BY TWO (2) HANGERS PER 10’ LENGTH, LOCATE HANGERS BETWEEN 6” to 24”
FROM EACH TUBE CONNECTION.
1ST & 2ND TUBES ONLY FROM BURNER END: INSTALL WELDED SEAM FACING DOWNWARD.
Stainless steel
rivet
IMPORTANT:
Torque nuts
to 40 lb-ft