Installation manual

Rinnai Australia - 13 - HOTFLO Electric Storage Water Heater Operating/Installation Manual
Commissioning and draining activities must be carried out by an authorised person.
To fill and turn ‘ON’ the water heater
Open all hot water taps in the house, including the shower.
Open the cold water isolation valve to water heater. Air will now be forced out of the taps.
Close each tap when water runs freely without air bubbles.
Check all plumbing connections and pipe work for water leaks.
Switch on the electric power supply.
To turn ‘OFF’ the water heater
It may be necessary to turn off a water heater after installation and commissioning, for example during building
activities or if the premises are vacant.
To turn ‘OFF’ the water heater:
Switch off the electricity supply at the isolating switch to the water heater.
Unplug the power supply cord from the power outlet (only for models fitted with power supply cord).
Close the cold water isolation valve at the inlet to the water heater.
Draining
To drain the water heater:
Turn off the water heater.
Close all hot water taps.
Operate the PTR valve release - gently. Operating the PTR valve release will relieve the pressure in the
water heater.
Undo the cold water inlet union. Attach a hose to the water heater side of the union. Let the other end of
the hose go to a drain.
Operate the PTR valve again. This allows air into the water heater and will result in water draining through
the hose.
Do not switch on the electric power supply until the water heater is filled completely with
water.
WARNING
COMMISSIONING