Technical data
34
 sized  to  ensure a  slope  of  10  mm  per  metre  of  length;  if  this  slope  cannot  be •
achieved, a condensate pump must be installed near to the discharge;
 realized in such a way as to prevent icing of the condensate;•
 mixed, for example, with domestic effluents (washing machine, dishwasher, etc.), •
usually alkaline, acting as a buffer solution before discharging into the sewer.
Do not discharge the condensate into the guttering, since it may ice and corrode the 
materials normally used for gutters.
5.6   FILLING OF HYDRAULIC CIRCUIT
After having completed all hydraulic, gas and electrical  connections, the installer can 
proceed filling the hydraulic circuit, observing the following steps:
You will need: the appliance connected hydraulically and electrically.
COLD CIRCUIT GAHP-GS
 Check that the system delivery and return are correctly connected to the appli-1. 
ance’s respective fittings (see Figure 3.1 Size → 15).
 Activate the automatic air purging valves of the plant and open all thermostatic 2. 
valves.
 Fill the hydraulic circuit to at least the minimum amount and add inhibited mo-3. 
noethylene glycol to a volume percentage of 25% (obligatory minimum required 
for correct system operation) or greater depending on the minimum winter tem-
perature in the installation area (see Table 5.3 Technical data for filling the hydraulic 
circuit → 36). Robur recommends using inhibited corrosion resistant monoethyl-
ene glycol.
 Check the filter on the return pipe for impurities; clean it if necessary.4. 
 Check that the siphon on the drainage condenses has been filled with water as 5. 
indicated in the relative paragraph.
 Bring the plant to the correct pressure, making sure that the water pressure is not 6. 
less than 1 bar and not over 2 bar, and run the circu lation pump for at least 30 min-
utes. Check the water filter again and clean it if necessary.
The technical data (Tables 3.1 GS HT/LT technical data → 12 and 3.2 WS technical da-
ta → 13) regarding the cold circuit refer to water with 25% glycol content, so that no 
correction factor need to be applied to Table 5.3 Technical data for filling the hydraulic 
circuit → 36.
To  facilitate  the  operation  of  bleeding  air  from  the  hydraulic  circuit,  the  appliance  is 
equipped with an additional manual air bleeding valve.
COLD CIRCUIT GAHP-WS 
 Check that the system delivery and return are correctly connected to the appli-1. 
ance’s respective fittings (see Figure 3.1 Size → 15).
 Activate the automatic air purging valves of the plant and open all thermostatic 2. 
valves.