Instructions / Assembly

2 February 16, 2018
of the well at the top of capstone near flange is no greater than 73”. The
wells will vary slightly and may be stretched or compressed to meet
these dimensions.
Please note: This is not an issue if not installing grate or cover.
5. Drill the other top hole on its mark.
6. Place the other concrete wedge anchor in this hole; seat it properly with
a hammer.
7. Lift the well onto this anchor and put a 1” diameter washer and nut on
the anchor. The window wells may be stretched or compressed slightly
to fit over the anchor.
8. Use the remaining holes in the window well flanges as a drill template to
drill the remaining holes. You may also drill additional holes into flange,
if so desired. Make sure the top two holes on each side and the bottom
holes are securely fastened. Use at least every other hole thereafter. This
gives you four corners securely fastened during backfill.
9. Place the remaining anchors in the holes, place 1” diameter washers
over the anchor bolts, and tighten all the nuts.
Please note: Address drainage prior to backfill.
Rockwell Window Wells
786 WEST 1200 N. STE.5 SPRINGVILLE UTAH 84663
PHONE 801-396-7020 FAX 801-396-7021
WEB: www.rockwellinc.com