16.0 Commencement of Works:
The date of commencement of the work will be reckoned as the date of handing over site by joint signature
of contractor, PMC & NLUO or three days from the date of issue of letter of acceptance of the tender by the
NLUO whichever is later.
17.0 Time for completion
Time is essence of the contract and shall be strictly observed by the contractor. The Work shall be completed
within a period of 120 calendar days from the date of commencement work. If required in the contract or as
directed by the Architect/ consultant. The contractor shall complete certain portions of work before
completion of the entire work. However the completion date shall be reckoned as the date by which the
whole work is completed as per the terms of the contract.
18.0. No compensation or restrictions of work
If at any time after acceptance of the tender NLUO shall decide to abandon or reduce the scope of work for
any reason whatsoever and hence not required the whole or any part of the work to be carried out. The
Architect/PMC/ shall give notice in writing to that effect to the contractor and the contractor shall act
accordingly. In the matter. The contractor shall have no claim to any payment of compensation or otherwise
whatsoever, on account of any profit or advantage which he might have derived from the execution of the
work fully but which he did not derive in consequence of the foreclosure of the whole or part of the work.
Provided that the contractor shall be paid the charges on the materials carried only actually and confide
brought to the site of the work by the contractor and rendered surplus as a result of the abandonment,
curtailment of the work or any portion thereof and then taken back by the contractor, provided however that
the NLUO shall have in such cases the option of taking over all or any such materials at their purchase price
or a local current rate whichever is less.
“In case of such stores credit shall be given to him at the rates not exceeding those at which were originally
issued to the contractor after taking into consideration and deduction for claims on account of any