NLUO PMC CONTRACTOR
SIGNATURE AND SEAL SIGNATURE AND SEAL SIGNATURE AND SEAL
deterioration or damage while in the custody of the contractor and in this respect the decision of PMC/
Consultant shall be final.
19.0 Suspension of work
i) The contractor shall, on receipt of the order in writing of the PMC/ Consultant (whose decision shall be final
and binding on the contractor) suspend the progress of works or any part thereof for such time and in such
manner as PMC/ Consultant may consider necessary so; as not to cause any damage or injury to the work
already done or endanger the safety thereof for any of following reasons.
a) On account any default on the part of the contractor, or
b) For proper execution of the works or part thereof for reasons other than the default of the contractor, or
c) for safety of the works or part thereof.
The contractor shall, during such suspension properly protect and secure the works to the extent necessary
and carry out the instructions given in that behalf by the PMC/ Consultant.
ii) If the suspension is ordered for reasons b) and c) in sub – Para I) above:
The contractor shall be entitles to an extension of time equal to the period of every such suspension. No
compensation whatsoever shall be paid on this account.
20.0 Action when the whole security deposit is forfeited
In any case in which under any clause or clauses of this contract, the Contractor by the PMC/ Consultant
shall have the power to adopt any of the following course as they may deem best suited to the interest of the